BOB'S WEB SITE
Work Logs Found: 400
Category Work Time: 795 Hours
 Date
Hours
Work Log Summary

Details

 08-10-2021
3.00
Did stuff I've done before
Details
       

 07-01-2021
3.00
Completed heating and cooling section
Details
       

 07-01-2021
3.00
Completed heating and cooling
Details
       

 06-30-2021
3.00
Heater cable installation
Details
       

 06-20-2021
3.00
Heater vent assembly and installation
Details
       

 06-19-2021
0.50
Vent hinges
Details
     

 06-16-2021
1.00
Overflow bottle and air filter
Details
       

 06-15-2021
2.00
Attached throttle control cable
Details
       

 06-12-2021
0.50
Problem attaching throttle control
       

 06-07-2021
3.00
Installed oil lines and Adel clamps
Details
       

 06-06-2021
2.00
Added oil tank
Details
       

 06-05-2021
3.00
Radiator hoses attached
Details
       

 06-01-2021
4.00
Installed oil cooler and radiator
Details
       

 05-23-2021
2.00
Assembling various fuse parts and priming engine c
Details
     

 05-20-2021
3.00
Complied with SB-00013
Details
       

 05-13-2021
2.00
Complied with SB-00023
Details
       

 03-23-2021
2.00
Routing throttle and fuel shutoff cables
Details
       

 03-21-2021
2.00
Throttle system control work
Details
       

 03-05-2021
1.00
Started on engine controls
Details
     

 02-27-2021
1.00
Completed section 47
Details
       

 02-22-2021
1.00
Set propeller pitch
Details
       

 02-22-2021
1.00
Set prop pitch
Details
       

 12-08-2020
0.50
Reinstalled muffler
Details
       

 12-04-2020
2.00
Reinstalled prop
Details
     

 12-03-2020
1.00
Primed spinner parts
Details
       

 12-01-2020
2.54
Nutplates on the spinner bulkheads
Details
     

 11-27-2020
0.50
Stalled on the muffler installation
Details
       

 11-26-2020
0.50
Exhaust/Muffler installation
Details
     

 11-20-2020
0.50
Drilled more holes in spinner
Details
     

 11-19-2020
2.00
Fabricated spinner cutout reinforcement clips
Details
     

 11-18-2020
2.00
Drilled spinner to rear spinner bulkhead
Details
       

 11-14-2020
1.00
Drilled spinner to forward spinner bulkhead
Details
     

 11-13-2020
0.50
Aligned spinner
Details
     

 11-10-2020
1.00
I found the magnets
Details
       

 11-09-2020
3.00
Assembled muffler/heat muff assembly
Details
       

 11-07-2020
0.10
ProSealed the pitot bushing
Details
     

 11-07-2020
2.00
Finished spinner cutouts and installed prop
Details
       

 11-04-2020
2.00
Finished pitot tube routing, started on spinner
Details
       

 11-02-2020
1.00
Installed pitot tube. Trying to figure out routing
Details
       

 11-01-2020
1.00
Began pitot installation
Details
     

 10-31-2020
0.20
Fully finished SD-00001 service bulletin
Details
     

 10-27-2020
1.50
Mostly finished with SD-00001
Details
       

 10-26-2020
1.50
Began replacing trim motor
Details
       

 10-23-2020
2.00
Riveted oil door to top cowling
Details
       

 10-15-2020
2.00
Finished inlets and added heat shield
Details
       

 10-13-2020
2.00
Sanded inlets
Details
       

 10-12-2020
3.00
Bonded filtered air box and NACA vent to bottom co
Details
       

 10-11-2020
2.00
Prepped filtered air box
Details
       

 09-13-2020
1.50
Bonded NACA vent to top cowling
Details
       

 09-12-2020
1.50
Smoothing out the cowling vents
Details
     

 09-07-2020
0.50
Epoxied cooling vents to top cowling
Details
       

 09-06-2020
1.50
Cut cooling fins
Details
       

 09-02-2020
3.00
Cowling close out
Details

 09-01-2020
3.50
Completed riveting cowling hinges
Details
       

 08-31-2020
1.50
Started riveting hinges
Details
       

 08-30-2020
2.00
Fiberglassing work on cowling
Details
       

 08-29-2020
3.00
Drilled cowling side hinges
Details
       

 08-28-2020
2.00
Preparing to drill side hinges to top cowling
Details
     

 08-25-2020
2.00
Drilled side hinges to bottom cowling
Details
       

 08-23-2020
1.00
Drilled aft hinges in bottom cowling
Details
       

 08-22-2020
2.00
More cowling trimming and fitting
Details
       

 08-13-2020
5.00
Finished aft trimming of bottom cowling
Details
       

 08-03-2020
3.00
Drilled top cowling; started fitting bottom cowl
Details
       

 08-02-2020
3.00
Trimming the top cowl
Details
       

 08-01-2020
1.50
Spacers for spinner back plate
Details

 07-31-2020
4.00
Fit the top cowling
Details
       

 07-30-2020
1.00
Finished cowling cutouts
Details
     

 07-28-2020
6.00
Cowling trimming
Details
       

 07-27-2020
4.00
Started on the cowling
Details
       

 07-26-2020
2.00
Completed Section 46 except for one little thing
Details
       

 07-25-2020
1.00
Clamped ECU wires
Details
     

 07-23-2020
0.25
Mounted ECU
Details
     

 07-22-2020
2.00
Fuse box work
Details
       

 07-20-2020
4.00
Heat shield and fuse box
Details
       

 07-18-2020
0.50
Cut firesleeve
Details
     

 07-17-2020
1.00
Retorqued engine bolts
Details

 07-16-2020
2.00
Hung the engine
Details
       

 07-15-2020
2.00
Drilled second engine mount hole
Details

 07-06-2020
3.00
Wired up crankshaft position wires
Details
       

 07-05-2020
4.00
Engine mount bolted to engine
Details
       

 07-04-2020
2.00
Engine mount to engine
Details
       

 07-02-2020
0.25
Disconnected water coolant hoses
Details
     

 06-30-2020
2.00
Completed Section 27
Details
       

 06-29-2020
0.10
Reference pictures for ROTAX
Details
       

 06-26-2020
2.00
Uncrated the ROTAX 912iS
Details
       

 06-24-2020
2.00
Making fuel filter lines
Details
       

 06-23-2020
2.00
Began fuel filter assembly
Details
       

 06-22-2020
1.00
Assembled fuel filter assembly
Details
     

 06-20-2020
2.00
Began assembling fuel filter
Details
       

 06-17-2020
2.00
Inventoried Powerplant kit
Details
     

 06-16-2020
6.00
Powerplant kit arrives
Details
       

 06-12-2020
2.00
Drilled out some rivets
Details
     

 05-26-2020
2.00
Repainted rollbar
Details
       

 05-24-2020
2.00
Prepped canopy frame and rollbar for painting
Details
       

 02-08-2020
1.00
Set breakout force on nosewheel
Details
     

 02-06-2020
1.50
Replaced nose gear leg
Details
       

 02-01-2020
2.00
Reinstalled flaperon controls
Details
       

 11-15-2019
1.40
Drilled remaining holes on flaperon control
Details
     

 11-09-2019
2.00
Drilled flaperon controls
Details
       

 11-06-2019
0.00
More on attaching wings
Details
       

 11-06-2019
3.00
Attached wings
Details
       

 10-20-2019
1.00
Prepped flaperon brackets
Details

 10-18-2019
2.00
Attached flaperons to wing
Details

 10-07-2019
1.00
Finished most of service bulletin
Details
       

 10-06-2019
1.50
Riveted gussets
Details
       

 10-04-2019
2.00
Assembled new hinge brackets
Details
     

 10-01-2019
2.00
Started on spar service bulletin
Details
       

 09-12-2019
2.00
Began prep of canopy
Details
       

 09-08-2019
2.00
Riveted side arms on canopy frame
Details
     

 09-07-2019
3.00
Fluted canopy frame brackets
Details
       

 08-31-2019
1.00
Mounted canopy frame
Details
     

 08-28-2019
2.00
Gas struts to canopy frame
Details
       

 08-21-2019
1.00
Started on canopy
Details
       

 08-18-2019
1.00
Final touches on fairing
Details
     

 08-14-2019
2.00
Finished (somewhat) nose gear fairing
Details
       

 08-13-2019
2.00
Drilled hinge to gear leg fairing
Details
     

 08-11-2019
2.00
Drilled gear leg fairing
Details
       

 08-02-2019
1.00
Started on gear leg fairing
Details
       

 07-31-2019
2.00
Finished nose wheel fairing
Details
       

 07-30-2019
1.00
Riveted nosewheel fairing brackets
Details
       

 07-28-2019
1.00
Riveted side brackets to nosewheel fairing
Details
       

 07-24-2019
4.00
Nosewheel fairing
Details
       

 07-03-2019
2.00
Finished right wheelpant
Details
       

 07-01-2019
2.00
Mounted right wheelpant
Details
       

 06-30-2019
1.00
Fit right wheelpant
Details
       

 06-21-2019
2.00
Started right wheelpant
Details
     

 06-20-2019
2.00
Completed left wheelpant
Details
       

 06-19-2019
2.00
Added epoxy to left wheelpant
Details
     

 06-15-2019
2.00
Fixed left wheelplant problem
Details
       

 06-09-2019
2.00
Identified left wheelpant problem
Details
       

 06-06-2019
2.00
Installed left wheelpant bracket
Details

 05-23-2019
1.00
Left axle work for wheelpant
Details
     

 05-22-2019
1.00
Landing gear cutout
Details
     

 05-19-2019
2.00
Sand forward half for mount fit
Details
     

 05-07-2019
1.00
Adjust left wheelpant cutout
Details
     

 04-23-2019
1.00
Trim wheelpant cutout
Details
       

 04-22-2019
1.50
Started on wheelpants
Details
       

 04-19-2019
1.00
Brake fluid added
Details
     

 04-16-2019
0.50
Nose gear fork to nose leg
Details
     

 04-03-2019
2.00
Bolted nose gear fork
Details
       

 03-24-2019
2.00
Brake lines
Details
       

 01-13-2019
2.00
Main gear installed
Details
       

 01-05-2019
2.00
Left side axle
Details
       

 01-02-2019
1.00
Finished left side gear leg
Details
       

 12-29-2018
4.00
Landing gear
Details
       

 12-16-2018
4.00
Finished main wheel assembly
Details

 12-11-2018
1.00
Main wheel and tire installation
Details
       

 12-01-2018
1.50
Tired
Details
       

 11-24-2018
1.50
Attached engine mount
Details
       

 11-23-2018
1.00
Flap motor
Details
       

 11-22-2018
2.00
Attached flap assembly control tubes
Details
       

 11-18-2018
0.50
Riveted control arms and primed tube
Details
       

 11-17-2018
1.00
Drilled rod end bearing males to control tubes
Details

 11-12-2018
1.00
Bolted control rods to flap control mechanism
Details
       

 11-10-2018
3.00
Tapped control rods
Details
       

 11-04-2018
3.00
Begin yoke installation
Details
       

 11-03-2018
2.00
Crontrol yoke bracket housing
Details
       

 10-30-2018
0.50
Started working on flap mechanism
Details
     

 10-28-2018
1.00
Installed pulleys
Details
       

 10-27-2018
1.50
Cable routing
Details
       

 10-20-2018
1.00
Added clamps to rudder cables
Details
       

 10-13-2018
1.50
Installed control column
Details
       

 10-05-2018
2.50
Prepped control rod and made support brackets
Details
       

 09-23-2018
1.00
Completed fuselage kit
Details

 09-22-2018
1.00
Riveted angle support to forward skin
Details
     

 09-05-2018
2.00
Added sealant to forward skin
Details
       

 09-03-2018
1.00
Riveted handle to supports
Details
     

 08-22-2018
2.00
Sealed side canopy rails
Details
     

 08-21-2018
3.00
Finished riveting forward deck
Details
       

 08-20-2018
2.00
Riveted canopy ribs on
Details
       

 08-16-2018
1.50
Rivet engine mount brackets
Details
     

 08-11-2018
3.00
Completed canopy ribs
Details
       

 08-10-2018
1.00
Adding remaining cowling hinge
Details
     

 08-09-2018
1.50
Began working on canopy ribs
Details
       

 08-08-2018
4.00
Sealed firewall
Details
       

 08-07-2018
2.00
Installed upper firewall
Details
       

 08-06-2018
2.00
Riveted hinge on forward firewall
Details
       

 08-05-2018
3.00
Began work on upper firewall
Details
       

 08-03-2018
1.00
Began on forward fuselage top
Details
     

 08-02-2018
1.00
Completed brake lines
Details
     

 07-31-2018
2.00
Started making brake lines
Details

 07-28-2018
2.00
Drilled brake pedals
Details
     

 07-25-2018
2.00
Expensive brake pedal screwup
Details

 07-23-2018
2.00
Brake pedal drilling
Details
     

 07-20-2018
2.00
Started on the rudder pedals
Details
       

 07-19-2018
2.00
Completed fuel lines (for now)
Details
       

 07-16-2018
1.00
Installed fuel valve
Details
     

 07-04-2018
2.00
More fuel lines
Details
       

 07-03-2018
2.00
Starting making fuel lines
Details
       

 07-01-2018
3.00
Fit the fuel tank
Details
       

 06-29-2018
2.00
Tank testing
Details
       

 06-19-2018
3.00
Finished sealing fuel tank
Details
       

 06-16-2018
1.00
Sealed fuel gauge
Details

 06-11-2018
5.00
Riveted bottom skin of fuel tank
Details
       

 06-01-2018
2.00
More fuel tank sealing
Details
       

 05-28-2018
7.00
Started sealing the fuel tank
Details
       

 05-17-2018
3.00
Nutplates and fuel tanks, oh my!
Details
       

 05-12-2018
1.00
Started on fuel tank
Details
       

 05-10-2018
1.00
Completed second seatback
Details

 05-09-2018
0.50
Started working on second seat
Details
     

 05-08-2018
1.00
Finished a seat back
Details
     

 05-07-2018
1.50
Seatback riveting
Details

 05-06-2018
2.00
Started on seatbacks
Details
       

 05-05-2018
2.00
Completed roll bar support
Details
       

 05-03-2018
0.50
Roll bar support
Details
     

 04-26-2018
4.00
Rear bulkhead
Details
       

 04-21-2018
0.25
Painted parts of rollbar assembly
Details
     

 04-20-2018
0.50
Removed rollbar
Details

 04-19-2018
2.00
Riveted support bracket
Details
     

 04-18-2018
2.00
Side rollbar support
Details
     

 04-15-2018
2.00
Prepping rollbar for riveting
Details
       

 04-11-2018
1.50
Deburred rollbar
Details
       

 04-09-2018
0.50
Finishing kit arrives
Details
     

 04-06-2018
1.00
Removed rollbar
Details

 04-05-2018
1.50
Finished drilling rollbar
Details

 04-04-2018
1.50
Started drilling rollbar
Details
     

 04-03-2018
1.50
Fitting rollbar
Details
     

 04-02-2018
2.00
Rollbar construction
Details
       

 04-01-2018
3.00
Completed section 23.
Details
       

 03-30-2018
2.00
Assembled fuselage vent doors
Details
       

 03-27-2018
4.00
Completed left side skin
Details
     

 03-25-2018
1.00
Added nutplates to left side skin
Details
     

 03-24-2018
3.00
Drilling right longeron
Details
     

 03-21-2018
3.00
Completed right side skin
Details
     

 03-17-2018
3.00
Began riveting side skin on right side
Details
     

 03-16-2018
1.50
Finished nutplates and primed right skin
Details
       

 03-15-2018
1.00
Deburring right skin
Details

 03-14-2018
3.00
Drilled longeron holes
Details
     

 03-07-2018
2.50
Finished wing cutouts in side skin
Details
       

 03-05-2018
1.00
Longerons
Details
       

 03-02-2018
1.00
Riveted forward "post"
Details
     

 02-28-2018
1.50
Countersunk longeron
Details

 02-27-2018
1.00
Attached one bulkhead plate
Details
     

 02-26-2018
1.50
Countersunk wrong side of doubler
Details

 02-25-2018
3.00
Riveted on seatbat crosspiece
Details
       

 02-24-2018
1.50
Primed longerons
Details
     

 02-23-2018
3.00
Drilled top plates to longeron
Details
     

 02-22-2018
2.00
Twisted longerons
Details
       

 02-19-2018
3.00
Completed mating of forward and mid fuselage
Details
       

 02-18-2018
5.00
Completed forward lower fuselage
Details
       

 02-17-2018
2.00
Bottom skin to firewall
Details
       

 02-16-2018
1.00
Completed firewall to bottom skin riveting
Details
       

 02-12-2018
1.00
Riveted bottom skin to 'ribs'
Details
     

 02-11-2018
4.00
Worked on firewall shelf etc,
Details
       

 02-08-2018
2.00
Firewall work
Details
       

 02-03-2018
1.00
Finished with missing rivets
Details
     

 02-02-2018
1.50
The case of the missing rivets
Details
     

 02-01-2018
1.50
Preppedt aft brackets
Details
     

 01-31-2018
1.00
Riveted aft bulkhead
Details

 01-30-2018
1.50
Riveted forward floors
Details
     

 01-29-2018
1.50
Prepped remaining forward floor
Details
     

 01-28-2018
4.00
Completed riveting bottom skin to structure
Details
       

 01-25-2018
0.75
Riveting bottom skin
Details
     

 01-24-2018
1.25
Riveted doublers/stringers to superstructure
Details
     

 01-21-2018
4.00
Fit bottom skin
Details
       

 01-18-2018
1.50
Prepped up angles
Details

 01-18-2018
1.00
Prepped bottom skin
Details
       

 01-17-2018
1.00
Riveted shark gills
Details

 01-16-2018
1.50
Began work on 'shark gills'
Details
     

 01-15-2018
3.00
Riveted forward floor ribs
Details
       

 01-13-2018
2.00
More work on forward bulkhead
Details
       

 01-10-2018
1.75
More riveting on aft bulkhead
Details
       

 01-09-2018
2.00
Fuselage rear bulkhead
Details
       

 01-07-2018
1.50
Added center section bulkhead caps and rollers
Details
       

 01-06-2018
1.50
Finished riveting floor/ribs to center section
Details
       

 01-04-2018
1.00
Started riveting floor ribs to center section
Details
     

 01-03-2018
2.00
Riveted right side floor ribs to floor
Details
     

 01-02-2018
1.50
Riveted left side ribs to floor
Details
     

 01-01-2018
2.00
Started fitting floors
Details
     

 12-31-2017
2.50
Riveted brackets
Details
       

 12-30-2017
2.50
More rib prep
Details
     

 12-29-2017
2.00
More seat rib work
Details
       

 12-28-2017
4.50
Started on seat ribs
Details
       

 12-27-2017
4.00
Pulley assembly and flaperon mixture arm
Details
       

 12-26-2017
1.00
Stuck with Cherry rivets
Details
     

 12-23-2017
3.00
Finished attaching ribs to floor and bulkhead
Details
       

 12-22-2017
1.00
Finished riveting flooors
Details
     

 12-20-2017
2.00
Attached left ribs to center section
Details
     

 12-19-2017
1.00
Finished right side baggage ribs
Details
       

 12-18-2017
1.50
Started riveting baggage ribs
Details
       

 12-17-2017
1.50
Attached nutplates to inspection holes
Details
     

 12-16-2017
1.00
Various puttering while waiting for backordered pa
Details
       

 12-12-2017
1.50
Riveted floors to center section
Details
       

 12-11-2017
1.00
Started Riveting floors
Details
       

 12-10-2017
2.00
Riveted ELT bracket to ribs
Details
       

 12-09-2017
2.00
ELT bracket
Details
       

 11-28-2017
1.50
More center section work
Details
       

 11-26-2017
3.00
Adding more parts to the center section
Details
       

 11-25-2017
2.00
Countersinking/dimping center section
Details
     

 11-24-2017
3.00
Finished drilling center section
Details
     

 11-22-2017
1.00
50 down, about 74 to go
Details
     

 11-20-2017
1.00
Fit center section to bottom skin
Details
       

 11-19-2017
1.00
Started on Center section
Details
     

 11-18-2017
0.10
Ready to start on fuselage
Details
       

 08-26-2017
3.00
Finished right wing light fairing
Details
       

 08-25-2017
1.50
Completed left light fairing
Details
       

 08-24-2017
1.00
Started on right wing position light installation
Details
       

 08-23-2017
3.00
More work on left wing lighting
Details
       

 08-22-2017
2.00
Epoxied the lighting fair (left)
Details
       

 08-13-2017
1.50
Cut access hole in left wing for outboard light
Details
       

 08-11-2017
1.00
Finishing work on left flaperon
Details
     

 08-10-2017
1.50
Completed right flaperon
Details
     

 08-09-2017
1.50
Flaperon skin riveting
Details
     

 08-08-2017
1.50
Riveted ribs etc to right flaperon
Details
       

 08-07-2017
1.50
Prep work on the right flaperon
Details
       

 08-05-2017
3.00
Started work on right flaperon
Details
     

 08-04-2017
1.50
Riveted skin to flaperon substructure
Details
     

 08-03-2017
1.50
Riveted ribs on flaperon
Details
       

 08-02-2017
1.50
Flaperon work
Details

 07-31-2017
1.50
Started on left flaperon
Details
       

 07-30-2017
5.00
Completed right wing
Details
       

 07-29-2017
4.50
Right wing closeout
Details
       

 07-26-2017
1.00
Riveted wing root doubler
Details
     

 07-25-2017
2.00
Started on wing root doubler
Details

 07-24-2017
2.00
Fit the top middle skin
Details

 07-23-2017
5.50
Finished landing light. Started out inboard top sk
Details
       

 07-22-2017
5.00
Began installing landing light
Details
       

 07-21-2017
2.00
Riveted bottom middle skin (right)
Details
     

 07-19-2017
1.00
Completed inboard out skin
Details

 07-17-2017
2.00
Completed inboard bottom skin (right)
Details
     

 07-16-2017
5.00
Began skinning right wing
Details
       

 07-15-2017
5.00
Finished left wing
Details
       

 07-14-2017
2.00
Fluted and riveted wing tip frame
Details
     

 07-11-2017
1.00
Worked on wing tips
Details
     

 07-09-2017
6.50
Completed top of left wing
Details

 07-08-2017
6.00
Started on top skins (left)
Details
       

 07-06-2017
1.50
Completed bottom skin (left)
Details
       

 07-05-2017
2.00
Started with the bottom center skin (left)
Details

 07-04-2017
6.00
Riveted inboard and outboard bottom skins (left)
Details
       

 07-02-2017
3.50
Began riveting skins
Details
       

 07-01-2017
2.00
Ran wires
Details
       

 06-30-2017
3.00
Stall warning
Details
       

 06-29-2017
2.00
Completed rib installation on right wing spar
Details
       

 06-28-2017
2.00
Began installation of right wing main ribs
Details
       

 06-25-2017
4.00
Wing rib riveting
Details
     

 06-24-2017
5.50
Began mounting ribs
Details
       

 06-23-2017
1.50
Completed nose ribs, worked on main ribs
Details
     

 06-21-2017
1.00
Worked on right nose ribs
Details

 06-20-2017
2.00
Finished 1208 L rib preparation
Details
       

 06-19-2017
1.00
Started working on ribs
Details
       

 06-17-2017
4.00
Completed rear spar
Details
       

 06-15-2017
2.00
Countersinking and priming
Details
       

 06-14-2017
1.00
Rivet hinge bracket assembly
Details
     

 06-13-2017
1.00
Riveted brackets
Details
     

 06-12-2017
1.00
Primed spar stub doubler
Details
     

 06-11-2017
2.00
Began rear spar doublers
Details
     

 06-10-2017
3.00
Riveted rib doublers
Details
       

 06-09-2017
2.00
Started work on wings
Details

 06-05-2017
2.00
Inventoried wing kit
Details
       

 03-28-2017
2.00
Completed empennage kit
Details
       

 03-27-2017
2.00
Wired connector for trim servo
Details
       

 03-26-2017
2.00
Assembled trim pushrods etc.
Details
     

 03-25-2017
3.00
Fit control surfaces to tailcone
Details
       

 03-24-2017
0.50
Fit vertical stabilizer
Details
       

 03-21-2017
1.50
Completed tailcone
Details
     

 03-19-2017
3.00
Began riveting top skin
Details
       

 03-18-2017
1.25
Fit the top tailcone skin
Details
     

 03-17-2017
1.50
Completed side skin riveting on tailcone
Details
       

 03-16-2017
1.00
Completed right side of side skin riveting
Details
       

 03-15-2017
0.75
More riveting of side skins
Details
     

 03-14-2017
1.00
Riveting side skins
Details
       

 03-13-2017
1.50
Prepped top corner skins
Details
       

 03-12-2017
2.50
Installed some system runs
Details
       

 03-11-2017
3.00
Completed riveting tail cone bottom
Details
       

 03-10-2017
1.50
More riveting of bottom skins
Details
     

 03-09-2017
3.00
Riveted bottom skin halfs
Details
     

 03-02-2017
1.00
Fit side skirts to tailcone
Details

 02-26-2017
1.00
Started work tail cone skin
Details
     

 02-25-2017
2.00
Fit aft bulkhead to stabilator
Details
       

 02-24-2017
1.00
Finished riveting aft bulkhead
Details

 02-23-2017
1.50
Riveting aft bulkhead
Details
     

 02-22-2017
0.50
Made tie-down bracket
Details
     

 02-20-2017
5.00
Assembled bulkheads
Details
       

 02-19-2017
1.50
Completed stabilator
Details
     

 02-18-2017
6.00
Finished riveting the stabilator
Details
       

 02-17-2017
1.50
Began riveting left skin on stabilator
Details
       

 02-16-2017
1.00
Completed right stabilator skin
Details

 02-15-2017
1.00
More riveting
Details
     

 02-14-2017
1.50
Reamed holes
Details
     

 02-12-2017
1.00
Fit skin on stabilator
Details
     

 02-11-2017
7.00
Completed stabilator spar assembly
Details
       

 02-10-2017
2.00
Riveted control brackets
Details
     

 02-09-2017
2.00
Riveted nutplates
Details
     

 02-08-2017
2.00
Spar box assembly
Details
       

 02-06-2017
0.50
Stabilator spar box assembly
Details
     

 02-05-2017
2.00
Stabilator parts prep
Details
       

 02-05-2017
1.00
More priming
Details
     

 02-05-2017
1.00
More part prep for stabilator
Details
       

 02-04-2017
2.00
Completed right anti servo tab assembly
Details
       

 02-03-2017
1.00
Started work on right trim assembly
Details

 02-02-2017
1.00
Completed left trim assembly
Details

 01-27-2017
3.00
Primed and riveted rudder parts
Details
       

 01-27-2017
4.00
Completed rudder
Details
       

 01-23-2017
3.00
Began work on rudder
Details
       

 01-22-2017
5.00
Completed vertical stabilizer
Details
       

 01-21-2017
4.00
Completed VS rib/spar assembly
Details
       

 01-20-2017
1.00
Riveted upper spar caps to rear VSspar

 01-17-2017
1.00
Completed other half of VS spar doubler

 01-16-2017
2.00
First parts for vertical stabilizer
     

 01-14-2017
2.00
Kit arrival and inventory
Details
       