Date:  2-28-2014
Number of Hours:  2.00
Manual Reference:  
Brief Description:  Started the Pre-Airworthiness Inspection

Started the Pre-Airworthiness Inspection. Completed the inspection of the exterior except for the empennage and the cowling (it is still being worked upon). I'll finish the interior inspection just before the Airworthiness Inspection because I don't want to pull off floor panels now and then again for the actual inspection. I did a thorough inspection of the interior before the floors were installed and I am confident that these areas are ready for inspection. When I pull the floors, the areas will get another good cleaning. Everything (dust and dirt) finds its way to below the floors.