Larry Winger's 601XL Project
Zodiac CH 650
Engine
76 Logs Found
Date
Hours
Work Log Summary
Details
10-08-2012
3.3
2 - Misc punch list items
Details
10-08-2012
2.0
1 - Misc. under cowling - replaced cowling
Details
10-07-2012
6.0
Completed & installed heat muff
Details
10-06-2012
2.8
Started fabricating SS heat muff
Details
10-01-2012
2.8
Moved carb heat muff and cabin heat valve
Details
08-17-2012
4.5
Tested and calibrated fuel flow
Details
08-04-2012
2.8
1 - Rewired fuel pumps
Details
08-03-2012
3.1
Wired fuel pumps
Details
08-02-2012
2.5
Wired igntion system
Details
08-01-2012
1.8
Completed OV protection/alternator wiring
Details
07-31-2012
3.5
Progress on alternator system wiring
Details
07-23-2012
3.5
Wired starter relay
Details
07-15-2012
1.0
2 - Connected oil temp and began oil pressure send
Details
07-15-2012
4.0
1 - Oil & filter changed and distributor set
Details
06-24-2012
2.5
Main wire to starter
Details
06-12-2012
0.8
Installed fuel pressure sender & fuel fittings
Details
06-10-2012
1.8
Re-pitched prop & installed firesleeve
Details
06-07-2012
0.8
Fuel line to carb and fuel filter installed
Details
06-06-2012
3.0
Re-routed 5th bearing oil line
Details
06-05-2012
3.3
Installed Floscan fuel meter
Details
06-04-2012
2.3
Installed fuel lines in cockpit and to carb
Details
10-11-2011
1.3
1 - Enlarged air inlets
Details
10-08-2011
8.8
1 - Installed spinner
Details
09-30-2011
1.3
2 - Marked spinner for cutouts
Details
09-30-2011
0.8
1 - Reinstalled intake manifold
Details
09-27-2011
3.8
Mounted and set adjustable prop
Details
09-14-2011
2.0
Installed cabin heat valve
Details
09-14-2011
1.8
Installed air filter box
Details
09-13-2011
2.8
Worked on mounting system for air filter box
Details
09-12-2011
3.3
Installed heat exchange muff
Details
09-12-2011
2.5
Completed heat exchange muff
Details
09-11-2011
3.3
Fabricated heat exchange muff
Details
09-10-2011
5.0
Fabricated air filter housing
Details
09-09-2011
3.0
Installed rubber baffle seals
Details
09-08-2011
1.8
Mounted 2.5" duct flange to carb bottom
Details
09-06-2011
2.5
Fitted the rubber baffle seal
Details
09-05-2011
5.0
Installed mixture control
Details
09-05-2011
3.0
Installed carb heat control and removed all cables
Details
09-04-2011
6.0
Made mixture control bracket and carb bottom plate
Details
09-03-2011
4.5
Installed throttle and linkage
Details
08-30-2011
2.8
Installed reverse throttle linkage
Details
08-27-2011
4.0
Installed engine stand-offs & alternator belt
Details
08-27-2011
1.5
Engine stand-offs fabricated
Details
12-04-2010
2.5
Temporary installed prop
Details
12-02-2010
1.5
Installed ignition wire to distributor
Details
12-01-2010
1.5
Installed oil lines to cooler
Details
11-29-2010
1.8
Mounted oil cooler
Details
11-28-2010
3.3
Moved alternator forward and mounted vertical baff
Details
11-27-2010
3.8
Installed exhaust system and worked on baffles
Details
11-26-2010
3.0
Added support tail to starter
Details
10-10-2010
3.3
Installed oil cooler baffling
Details
10-09-2010
8.0
Alternator mounted and baffling nearly complete
Details
10-08-2010
2.8
Started baffling work and alternator
Details
10-04-2010
1.0
Remounted engine
Details
10-03-2010
32.0
Brought my Corvair engine to life
Details
09-29-2010
3.0
Removed engine and packed for Corvair College 18
Details
01-12-2010
1.5
Intake manifold installed
Details
01-12-2010
1.0
Engine mounted
Details
01-08-2010
1.0
Installed battery connector in firewall
Details
01-07-2010
1.5
Fabricated & installed coil wires
Details
01-06-2010
3.0
Installed breather outlet tube & condensers
Details
01-04-2010
35.0
Installed ignition coils
Details
01-03-2010
0.8
Added hoses to oil breather
Details
01-02-2010
2.0
Installed oil separator and coil switcher
Details
12-29-2009
1.3
Installed firewall pass through
Details
10-31-2009
6.0
Added rigid fuel lines
Details
10-25-2009
6.0
Installed gascolator and fuel pumps
Details
10-21-2009
1.5
Installed rear housing and gold oil system
Details
10-10-2009
2.0
Engine Rear Housing Installed and Removed
Details
01-18-2009
0.0
Corvair College 13 and my new engine
Details
12-13-2007
1.5
Made first set of braided fuel lines
Details
02-24-2007
0.0
Received Corvair engine mount
Details
08-14-2006
2.0
Cleaned and stored engine parts
Details
08-12-2006
6.0
Disassembled and partially cleaned Corvair engine
Details
08-01-2006
0.0
Pickup Corvair engine
Details
07-27-2006
0.0
Found Corvair engine
Details
SITE NAVIGATION
Contact Builder
Zodiac CH 650 Home
All
Avionics
Empennage
Engine
Fuselage
Miscellaneous
None
Planning
Shop Supplies
Tools
Total Hours
Wings
Work Area
Copyright © 2001-2013 Matronics. All Rights Reserved.