Work Logs Found: 448
Category Work Time: 894 Hours
 Date
Hours
Work Log Summary

Details

 09-10-2017
2.20
Wing CS Spar
Details
       

 09-09-2017
4.10
Wing CS Spar internal layup
Details
       

 09-02-2017
0.10
Wing CS Spar internal layup
Details

 09-01-2017
6.50
Wing CS Spar internal layup
Details
       

 08-30-2017
1.00
Wing CS Spar
Details

 08-29-2017
1.00
Wing CS Spar
Details

 08-28-2017
1.00
Wing CS Spar
Details
     

 08-25-2017
0.80
Wing CS Spar
Details
     

 08-24-2017
2.00
Wing CS Spar parts
Details
       

 08-23-2017
1.90
Wing CS Spar foam
Details
       

 08-22-2017
2.40
Wing CS Spar foam
Details
       

 08-21-2017
1.50
Wing CS Spar foam
Details
     

 08-20-2017
1.00
Wing CS Spar foam
Details
       

 08-19-2017
3.80
Wing CS Spar jig
Details
       

 08-18-2017
1.90
Wing CS Spar jig
Details
       

 08-17-2017
3.30
Wing CS Spar jig
Details
     

 08-14-2017
4.10
Wing CS Spar jig
Details
       

 07-25-2017
0.00
Finger on the building switch
Details
       

 10-19-2016
0.10
Why I haven't updated for ages
Details
       

 04-20-2016
1.00
Canard Brace
Details
     

 04-19-2016
1.00
Canard brace
Details
     

 04-06-2016
0.70
Fuselage bearing supports
Details
       

 04-02-2016
0.80
Nose and static point
Details
       

 03-31-2016
0.50
Static source
Details
       

 03-30-2016
1.20
Ballast Compartment
Details
       

 03-29-2016
0.60
Ballast Compartment
Details

 03-28-2016
1.20
Ballast Compartment/Nose door
Details
     

 03-28-2016
1.00
Ballast Compartment/ Nose Door
Details

 03-23-2016
0.80
Ballast Compartment
Details
     

 03-20-2016
0.10
Ballast Compartment
Details

 03-17-2016
1.00
Ballast Compartment & pitot
Details
       

 03-16-2016
1.10
Ballast Compartment
Details
       

 03-15-2016
1.00
Ballast Compartment
Details
       

 03-14-2016
1.40
Ballast Compartment
Details
       

 03-12-2016
1.90
Ballast Compartment
Details
       

 03-02-2016
1.60
Ballast Compartment
Details
       

 02-27-2016
4.20
Ballast Compartment
Details
       

 02-26-2016
1.50
Ballast Compartment
Details
       

 02-22-2016
1.20
Ballast Compartment
Details
     

 02-17-2016
0.60
Ballast Compartment
Details
       

 02-15-2016
1.00
Ballast Compartment
Details
       

 02-14-2016
1.70
Ballast Compartment
Details
     

 02-13-2016
4.60
Ballast Compartment
Details
       

 02-12-2016
1.10
Ballast Compartment
Details
       

 02-11-2016
1.50
Ballast Compartment
Details
       

 02-10-2016
1.50
Ballast Compartment
Details
       

 02-09-2016
0.40
Ballast Compartment
Details
       

 02-08-2016
0.80
Ballast Compartment
Details
       

 02-07-2016
2.30
Ballast Compartment
Details
       

 02-06-2016
2.40
Ballast Compartment
Details
       

 02-04-2016
1.30
Reattach Nose top
Details
       

 02-02-2016
0.30
Nose Bumper
Details
       

 02-01-2016
1.00
Nose upper skin
Details
       

 01-31-2016
0.50
Nose upper skin
Details
       

 01-30-2016
2.00
Nose upper skin
Details
       

 01-28-2016
0.40
Nose upper skin
Details
       

 01-27-2016
0.90
Nose upper skin
Details
       

 01-26-2016
5.80
Nose upper skin
Details
       

 01-25-2016
1.20
Nose door
Details
       

 01-24-2016
1.70
Nose door
Details
       

 01-22-2016
0.30
Nose Door
Details
       

 01-21-2016
1.30
Nose Top foam
Details
       

 01-20-2016
0.80
Nose top foam
Details
       

 01-19-2016
1.40
Nose top foam
Details
       

 01-18-2016
0.80
Nose top foam
Details
       

 01-17-2016
1.30
Nose top foam
Details
       

 01-16-2016
1.50
Nose gear doors
Details

 01-15-2016
0.80
Nose gear doors
Details
       

 01-14-2016
0.70
Nose gear doors
Details
       

 01-13-2016
1.00
Nose gear doors
Details
     

 01-12-2016
0.50
Nose gear doors
Details
       

 01-11-2016
0.60
Nose gear doors
Details
       

 01-10-2016
2.60
Nose gear doors
Details
       

 01-07-2016
1.10
Nose gear doors
Details
       

 01-02-2016
3.50
Nose gear doors
Details
       

 01-01-2016
2.20
Nose gear doors
Details
       

 12-31-2015
2.80
Nose gear doors
Details
       

 12-30-2015
0.90
Nose gear doors and outer cover
Details
       

 12-29-2015
2.00
Nose gear doors and outer cover
Details
       

 12-28-2015
2.10
Outer strut cover
Details
       

 12-27-2015
1.20
Trimming lower nose layup
Details
       

 12-26-2015
2.30
Nose lower skin layup
Details
       

 12-23-2015
3.20
Preparing for lower nose skin
Details
       

 12-22-2015
0.60
Shaping the nose
Details
       

 12-21-2015
1.60
Shaping the nose
Details
       

 12-16-2015
2.00
Fitting SC and Puck reinforcement
Details
       

 12-11-2015
3.40
Shaping the Nose
Details
       

 12-09-2015
1.80
Nose Cone
Details
     

 12-05-2015
1.00
Nose Cone
Details
     

 12-01-2015
0.40
Nose Cone
Details
       

 11-29-2015
2.00
Nose Cone
Details

 11-27-2015
1.30
Nose Cone
Details

 11-25-2015
2.00
Nose Cone
Details
     

 11-24-2015
2.10
Nose Cone
Details
       

 11-20-2015
2.20
Nose Cone & top, and Ballast Compartment
Details
     

 11-18-2015
4.90
Fitting Nose Gear and Rudder Pedals
Details
       

 11-16-2015
2.60
Fitting Nose Gear and Rudder Pedals
Details
       

 11-15-2015
1.70
Fitting Nose Gear & Rudder Pedals
Details
       

 11-14-2015
8.00
Fitting Nose Gear & Rudder Pedals
Details
       

 11-12-2015
2.30
Fitting Nose Gear, preparing to fit Rudder Pedals
Details
       

 11-11-2015
1.70
Fitting Nose gear
Details
       

 11-09-2015
1.40
Canard mounts and rudder pedals
Details
       

 11-08-2015
2.70
Canard mounts and rudder pedals
Details
       

 11-07-2015
2.70
Canard mounts and rudder pedals
Details
       

 11-06-2015
1.70
Canard mounts
Details
       

 11-05-2015
0.90
Fitting Nose Gear
Details
       

 11-02-2015
3.80
Nose sides and Nose Gear
Details
       

 11-01-2015
0.30
Nose Gear & rudder pedals
Details

 10-31-2015
5.50
Nose sides
Details
       

 10-28-2015
3.00
Nose sides
Details

 10-27-2015
1.30
Nose sides
Details
       

 10-19-2015
1.70
Nose sides
Details
       

 10-18-2015
1.00
Nose floor and sides
Details
       

 10-16-2015
2.90
Nose floor
Details
       

 10-15-2015
3.00
Nose floor
Details
       

 10-15-2015
2.40
Glassing nose floor
Details
       

 10-14-2015
6.00
Fitting NG-30 assembly to nose
Details
       

 10-13-2015
3.30
Assembly NG-30
Details
       

 10-11-2015
3.60
Assembling Nose Strut
Details
       

 10-06-2015
1.50
Fitting NG-5
Details
       

 10-05-2015
1.30
Assembling NG-30 hardware
Details
       

 10-03-2015
2.00
Trial assembly NG-30
Details
       

 10-02-2015
1.80
NG-30 nose pivot mount
Details
       

 10-01-2015
1.60
NG-30 trimming & drilling
Details
       

 09-30-2015
2.20
NG-30 outer layup
Details
       

 09-29-2015
1.70
Nose Strut and NG-30
Details
       

 09-27-2015
0.80
Nose Strut wrap and NG-30
Details
       

 09-25-2015
2.60
Nose Strut wrap and NG-30
Details
       

 09-24-2015
0.70
Nose Strut wrap and NG-30
Details
       

 09-23-2015
1.00
Nose Strut wrap and NG-30
Details
       

 09-22-2015
3.30
Nose Strut wrap and NG-30
Details
       

 09-21-2015
1.00
Preparing Nose Gear Strut
Details
       

 09-21-2015
0.90
Finishing up Canard installation
Details

 09-18-2015
0.90
Fixing Canard rear attach pins
Details
       

 09-17-2015
0.50
Fixing Canard rear attach pins
Details
       

 09-16-2015
2.00
Fitting Elevators
Details
       

 09-15-2015
0.80
Finishing Canard rear tabs
Details
       

 09-14-2015
1.00
Attaching Canard rear tabs
Details
       

 09-13-2015
2.90
Fitting Canard rear tabs
Details
       

 09-12-2015
2.30
Aligning the Canard
Details
       

 09-11-2015
0.60
Aligning the Canard
Details
       

 09-10-2015
1.20
Preparing Canard locating pins
Details
       

 09-05-2015
2.00
Canard tips and Elevator counterweights
Details
       

 09-04-2015
1.90
Canard tips and Elevator counterweights
Details
       

 09-01-2015
1.40
Elevator counterweights
Details
       

 08-29-2015
1.40
Canard tips and elevator counterweight
Details
       

 08-25-2015
0.10
Canard tips
Details

 08-23-2015
0.10
Canard tips
Details

 08-22-2015
0.40
Canard tips
Details
       

 08-17-2015
0.60
Canard tips
Details
       

 08-15-2015
2.60
Canard tips
Details
       

 08-14-2015
2.60
Canard tips
Details
       

 08-13-2015
1.60
Canard tips
Details
       

 08-10-2015
1.30
Canard tips
Details
       

 08-08-2015
2.00
Canard tips
Details
       

 08-04-2015
1.20
Canard tips
Details
       

 08-03-2015
0.50
Mounting Elevators on Canard
Details
     

 08-02-2015
4.90
Mounting Elevators on Canard
Details
       

 08-01-2015
1.00
Mounting Elevators on Canard
Details
       

 08-01-2015
0.10
Mounting Elevators on Canard
Details
       

 07-28-2015
0.70
Assembling Elevators
Details
       

 07-27-2015
4.30
Assembling Elevator hardware
Details
       

 07-23-2015
0.80
Assembling Elevator Hardware
Details
       

 07-22-2015
2.00
Assembling Elevator hardware
Details
       

 07-19-2015
1.20
Assembling Elevator hardware
Details
       

 07-14-2015
0.30
Assembling Elevator hardware
Details

 07-13-2015
1.20
Trimming Elevator top skin layup
Details
       

 07-12-2015
1.50
Trimming Elevator top skin layup
Details
       

 07-10-2015
4.40
Elevator upper skin layup
Details
       

 07-09-2015
2.50
Preparing for Elevator upper skin layup
Details
       

 07-08-2015
1.10
Preparing for Elevator upper skin layup
Details
       

 07-07-2015
1.50
Elevator bottom skin layup
Details
       

 07-06-2015
1.80
Preparing for Elevator bottom skin layup
Details
       

 07-05-2015
0.70
Fitting Elevator cores to Torque Tubes
Details
       

 07-04-2015
3.20
Fitting Elevator cores to Torque Tubes
Details
       

 07-03-2015
0.70
Completing Canard
Details
       

 07-03-2015
0.70
Assembling Elevator hardware
Details
       

 07-01-2015
1.00
Finishing Canard
Details
       

 06-30-2015
1.30
Removing Canard from jigs
Details
       

 06-29-2015
0.70
Trimming Canard upper skin layup
Details
       

 06-29-2015
0.90
Assembling Elevator hardware
Details
       

 06-28-2015
4.50
Canard upper skin layup #2
Details
       

 06-21-2015
1.70
Preparing for Canard upper skin layup #2
Details
       

 06-20-2015
0.60
Preparing for Canard upper skin layup #2
Details
       

 06-16-2015
0.80
Preparing for Canard upper skin layup #2
Details
       

 06-14-2015
3.30
Preparing for Canard upper skin layup #2
Details
       

 06-13-2015
4.70
Remove Canard crap upper skin layup
Details
       

 06-10-2015
2.30
Inspecting Canard upper skin layup
Details
       

 06-09-2015
0.50
Inspecting Canard upper skin layup
Details
       

 06-08-2015
3.00
Canard upper skin layup
Details
       

 06-05-2015
2.00
Preparing Canard for upper skins
Details
       

 05-31-2015
1.50
Trimming Canard upper spar cap
Details
     

 05-30-2015
6.30
Canard upper spar cap layup
Details
       

 05-28-2015
1.70
Preparing for Canard upper spar cap
Details
       

 05-27-2015
1.50
Preparing for Canard upper spar cap
Details
       

 05-26-2015
3.10
Preparing for Canard upper spar cap
Details
       

 05-22-2015
2.00
Resolving Canard level issue
Details
       

 05-21-2015
0.80
Preparing for Canard upper spar cap
Details
     

 05-20-2015
1.50
Preparing for Canard upper spar cap
Details
       

 05-19-2015
1.70
Preparing for Canard upper spar cap
Details
       

 05-18-2015
0.30
Inspecting Canard lower skin layup
Details

 05-17-2015
1.90
Canard lower skin layup
Details
       

 05-13-2015
0.10
Preparing for Canard lower skin layup
Details
     

 05-12-2015
4.20
Preparing for Canard lower skin layup
Details
       

 05-10-2015
1.80
Trimming Spar Cap
Details
       

 05-09-2015
3.00
Laying up Canard Lower Spar Cap
Details
       

 05-08-2015
1.30
Fit Outer Canard Cores
Details
       

 05-06-2015
1.20
Fitting LE Canard cores
Details
       

 05-05-2015
0.50
Preparing to fit LE Canard cores
Details
     

 05-04-2015
0.70
Preparing to fit LE Canard cores
Details
     

 04-28-2015
1.20
Preparing to fit LE Canard cores
Details
     

 04-25-2015
1.20
Preparing to fit LE Canard cores
Details
       

 04-24-2015
4.00
Preparing to fit LE Canard cores
Details
     

 04-23-2015
2.10
Preparing to fit LE Canard cores
Details
       

 04-22-2015
1.10
Fit Canard Attach Tabs
Details
       

 04-19-2015
6.50
Shear Web layup
Details
       

 04-18-2015
4.20
Preparation for Shear Web
Details
       

 04-15-2015
1.50
Preparing for Shear Web
Details
       

 04-14-2015
2.00
Preparing for Shear Web
Details
       

 04-13-2015
3.30
Preparing for Canard Shear Web
Details
       

 04-12-2015
3.00
Trimming Canard Cores
Details
       

 04-12-2015
1.00
Cutting Elevator Cores
Details
     

 04-08-2015
0.80
Cutting Elevator Cores
Details
       

 04-05-2015
4.70
Cutting Canard Cores
Details
       

 04-04-2015
3.00
Cutting Canard Cores
Details
       

 04-01-2015
0.30
MLG Inner Cover trimming
Details
       

 03-31-2015
6.80
MLG Inner Cover install
Details
       

 03-30-2015
0.90
MLG Inner Cover prep
Details
       

 03-29-2015
1.50
Brakes and MLG trial install
Details
       

 03-27-2015
3.50
MLG Brakes
Details
       

 03-25-2015
1.50
MLG Inner Cover trimming
Details
       

 03-24-2015
1.50
MLG Inner Cover inner layup #2
Details
       

 03-16-2015
4.30
MLG Outer Cover fit nutplates
Details
     

 03-14-2015
2.10
MLG Covers, flange and disasters
Details
       

 03-13-2015
2.80
MLG Outer Cover flange, Inner Cover prep
Details
       

 03-12-2015
2.10
MLG Outer Cover flange
Details
       

 03-08-2015
0.50
MLG Outer Cover flange
Details

 03-04-2015
0.50
MLG Outer Cover flange
Details
       

 03-03-2015
2.60
MLG Axle finish installation
Details
       

 03-02-2015
0.20
MLG Axle install
Details
       

 03-01-2015
0.20
MLG Axle install
Details
     

 02-27-2015
0.20
MLG Axle install
Details
       

 02-26-2015
2.00
MLG Axle install
Details
       

 02-25-2015
2.20
MLG Axle install
Details
       

 02-24-2015
1.40
MLG Axle install
Details
       

 02-23-2015
1.30
MLG Axle install
Details
       

 02-19-2015
4.00
MLG Axle install
Details
       

 02-18-2015
1.50
MLG Axle install
Details
       

 02-17-2015
1.00
MLG Axle install
Details
       

 02-16-2015
4.50
MLG Axle install
Details
       

 02-12-2015
2.30
MLG Axle prep
Details
       

 02-11-2015
1.50
MLG Outer Cover, Axle preparation
Details
       

 02-10-2015
6.50
MLG Outer Cover, LB install
Details
       

 02-09-2015
2.50
MLG Outer Cover, LB install
Details
       

 02-08-2015
0.10
MLG Outer Cover
Details

 02-07-2015
1.40
MLG Outer Cover
Details
     

 02-06-2015
3.00
MLG Outer Cover, Landing Brake install
Details
     

 02-05-2015
6.20
MLG Tabs and Outer Cover. LB repair
Details
       

 02-03-2015
2.10
MLG Outer Cover
Details
       

 02-02-2015
4.20
MLG Attach Tab completion
Details
       

 02-01-2015
4.80
MLG Attach
Details
       

 01-31-2015
3.00
Fitting MLG
Details
       

 01-29-2015
2.20
MLG align with Fuselage
Details
       

 01-28-2015
2.20
Aligning MLG Strut with Fuselage
Details
       

 01-26-2015
1.30
MLG Attach Tab trimming
Details
       

 01-25-2015
7.10
MLG Tab inner layup. LB fus layup
Details
       

 01-24-2015
1.50
MLG Attach Tabs
Details
     

 01-23-2015
1.50
MLG Attach Tabs
Details
       

 01-21-2015
1.00
MLG tabs & Landing brake Hinge
Details
       

 01-20-2015
0.50
Prep Canard Jigs
Details

 01-20-2015
2.80
MLG Attach Tab layups
Details
       

 01-19-2015
1.20
Prep for MLG Tabs
Details
       

 01-18-2015
2.30
Prep for MLG Tabs
Details
     

 01-17-2015
0.20
Prep for MLG Tabs
Details
     

 01-16-2015
1.10
Prep for MLG Tabs
Details
       

 01-15-2015
7.00
Prep for MLG tabs and LB attach
Details
       

 01-14-2015
6.80
2nd torsional layup
Details
       

 01-13-2015
2.00
Preparation for 2nd torsional layup
Details
       

 01-12-2015
2.00
Brakeline conduit / LB hinge
Details
       

 01-10-2015
2.30
Brakeline conduit
Details
       

 01-09-2015
3.50
!st torsional layup
Details
       

 01-08-2015
3.00
Preparation, also other Chapters
Details
       

 12-16-2014
0.50
NG-5 / Wheel Cover
Details

 12-16-2014
0.30
Canard Templates
Details

 12-15-2014
0.50
NG-30 / MKNG-6 Doublers
Details
       

 12-15-2014
1.20
Canard Templates
Details
       

 12-13-2014
1.00
NG-30 / MKNG-6 doublers
Details
       

 12-12-2014
0.30
NG-30/MKNG-6 doublers
Details
       

 12-12-2014
0.30
Canard Templates
Details
     

 12-10-2014
3.00
Templates & Wire Saw
Details
       

 12-10-2014
3.00
MG-1 & 2
Details
       

 12-09-2014
7.80
Landing Brake hardware/MG-2
Details
       

 12-09-2014
3.50
1st torsional layup
Details
       

 12-08-2014
1.60
Landing Brake preparation
Details
       

 12-06-2014
0.50
Cut out Landing Brake
Details
     

 12-04-2014
1.30
Canard Templates and dowels
Details
       

 12-04-2014
2.70
Al hard points for MLG, Landing Brake
Details
       

 12-02-2014
1.00
Canard and Elevator Templates
Details

 11-28-2014
3.00
MLG strut preparation
Details
       

 11-26-2014
0.10
Motivation
Details

 11-13-2014
2.00
MLG Fairings
Details

 11-12-2014
1.00
Buying Stuff
Details

 11-11-2014
1.50
Main Landing Gear - Strut fairings
Details
       

 10-31-2014
0.10
Building Switch ON!
Details

 10-14-2014
2.00
Canard and Elevator Templates
Details
       

 10-09-2014
1.00
Canard and Elevator Templates
Details

 10-05-2014
4.00
Canard and Elevator templates
Details

 09-30-2014
1.00
Main Landing Gear - Fuselage reinforcement
Details

 09-25-2014
2.00
Prepare MLG strut
Details
       

 09-22-2014
2.50
Fuselage reinforcement / Trim MLG Strut
Details
       

 09-14-2014
0.20
Fuselage reinforcement
Details

 09-13-2014
0.50
Fuselage reinforcement
Details
     

 09-12-2014
2.50
Fuselage reinforcement
Details
       

 09-10-2014
4.70
Fuselage reinforcement
Details
       

 09-08-2014
1.50
Fuselage reinforcement
Details
       

 09-08-2014
0.50
Center seatbelt mount
Details
       

 09-07-2014
3.30
Center seatbelt mount
Details
       

 09-06-2014
1.70
Rear heat duct
Details
       

 09-05-2014
2.00
Rear heat duct
Details
       

 09-02-2014
2.50
Outer seat belt mounts / Rear heat duct
Details
       

 09-01-2014
2.50
Outer seat belt mounts / Rear heat duct
Details
       

 08-30-2014
1.50
Outer seat belt mounts
Details
       

 08-29-2014
1.00
Outer seat belt mounts / Rear heat duct
Details
       

 08-28-2014
2.80
Outer seat belt mounts
Details
       

 08-25-2014
2.60
Outer seat belt mounts
Details
       

 08-24-2014
1.50
Outer seat belt mounts
Details
       

 08-23-2014
3.00
Outer seat belt mounts
Details
       

 08-14-2014
0.60
Unwrap Struts and have a play
Details
       

 08-14-2014
1.00
Cleaning up some bits
Details
       

 07-31-2014
0.10
Glassing the sides
Details

 07-30-2014
1.50
Glassing the sides
Details
       

 07-29-2014
1.10
Trimming the sides
Details
       

 07-28-2014
3.00
Glassing the sides
Details
       

 07-27-2014
2.80
Glassing the sides
Details
       

 07-25-2014
3.00
Glassing the sides. Preparation
Details
       

 07-24-2014
0.60
Glassing the sides. Preparation
Details
       

 07-22-2014
2.00
Glassing the sides. Preparation
Details
       

 07-21-2014
0.50
Prepare sides
Details
     

 07-20-2014
0.50
Prepare sides
Details
     

 07-18-2014
2.00
Upper Fuselage profile
Details
       

 07-17-2014
2.00
Upper Fuselage profile
Details
       

 07-16-2014
0.50
Upper Fuselage profile
Details

 07-15-2014
3.50
Trim forward Fuselage
Details
       

 07-14-2014
0.50
Trim Fuselage bottom
Details
       

 07-12-2014
5.30
Glass Fuselage bottom
Details
       

 07-09-2014
4.00
Plug some holes in the shed
Details

 07-05-2014
1.00
Fix foam near spar carry-through
Details
       

 07-04-2014
3.30
Final preparation for bottom layup
Details
       

 07-02-2014
1.50
Landing brake
Details
       

 07-01-2014
2.20
Trim NACA
Details
       

 06-29-2014
1.70
Glassing NACA
Details
     

 06-28-2014
3.30
Ongoing shaping of bottom profile
Details
       

 06-27-2014
1.70
Ongoing bottom profile
Details
       

 06-26-2014
2.40
Profiling NACA foam
Details
       

 06-25-2014
2.00
Install NACA foam
Details
       

 06-24-2014
0.50
More foam shaping
Details
     

 06-23-2014
1.70
MLG Bulkhead cross pieces
Details
     

 06-22-2014
0.30
Trim tapes. Finish Chapter 06!
Details
     

 06-22-2014
4.30
Cut NACA foam
Details
       

 06-21-2014
2.50
Taping right side
Details
       

 06-20-2014
2.30
Taping right side
Details
       

 06-19-2014
2.30
Taping bottom, Left side
Details
       

 06-17-2014
0.80
Preparing for taping
Details
       

 06-16-2014
2.10
Fit Fuselage Bottom
Details
       

 06-15-2014
4.00
Layup Bottom interior
Details
       

 06-13-2014
1.00
Re-mark side windows
Details
       

 06-12-2014
2.00
Preparing bottom for internal glass
Details
       

 06-11-2014
2.10
Install bottom spacers
Details
       

 06-09-2014
3.50
Cut bottom spacers
Details
     

 06-08-2014
0.20
Finish cutting out landing brake
Details

 06-07-2014
2.50
Profile bottom foam
Details
       

 06-06-2014
6.00
Trim Heat Duct. Prepare bottom foam
Details
       

 06-04-2014
5.00
Install Heat Duct & Seatbrace. Some cleanup
Details
       

 06-03-2014
2.00
Heat Duct & Seatbrace external layup
Details
       

 06-02-2014
1.50
Repair Keel/Heat Duct
Details
       

 05-30-2014
2.00
Trial assemble Heat Duct & Seatbrace and discover
Details
     

 05-29-2014
1.00
Assemble Seatbrace
Details

 05-28-2014
4.20
Assemble Keel/Heat Duct & Seatbrace
Details
       

 05-27-2014
4.00
Fitted Lower Permanent Firewall
Details
       

 05-26-2014
2.00
MLG Bulkhead reinforcement
Details
       

 05-24-2014
1.90
Preparing Seat Brace and Heat Duct
Details
       

 05-23-2014
1.30
Invert fuselage
Details
     

 05-22-2014
4.00
Taping F28 & FWD MLG Bulkhead
Details
       

 05-21-2014
0.80
Fit FWD Upper MLG Bulkhead
Details
     

 05-19-2014
0.80
Finishing off last task
Details
       

 05-18-2014
1.50
Fit FWD Main Landing Gear Bulkhead
Details
       

 05-15-2014
1.50
Install
Details
       

 05-14-2014
1.50
Preparing for F28 installation
Details
       

 05-12-2014
3.20
Taping bulkheads
Details
       

 05-07-2014
5.80
Initial side assembly
Details
       

 05-02-2014
0.70
Trial assembly on table
Details
     

 04-30-2014
2.30
Fuselage trial assembly
Details
     

 04-29-2014
1.00
Setting up front shed for trial assembly
Details
     

 04-28-2014
5.30
Trial fit bulkheads
Details
       

 04-27-2014
2.00
Finish the sides
Details
       

 04-26-2014
3.10
Finish foam between LWY/LWX/Lower Longerons
Details
       

 04-25-2014
3.00
Rear woodwork
Details
     

 04-24-2014
5.00
Trim sides, finish electrical channel.
Details
       

 04-23-2014
7.50
Finish and glass upper longerons
Details
       

 04-22-2014
4.50
Fit upper longerons
Details
       

 04-20-2014
2.00
layup inner side
Details
       

 04-19-2014
0.70
Prepare for inner glass
Details
       

 04-18-2014
0.70
Prepare side windows
Details
     

 04-17-2014
5.60
Make and attach spacers
Details
       

 04-16-2014
1.80
Joined side foam
Details
       

 04-15-2014
1.80
Finished formwork
Details
       

 04-14-2014
3.00
Fuselage sides - erected side formwork
Details
       

 04-13-2014
1.50
Upper Longerons - Laminate
Details
       

 04-11-2014
2.00
Upper Longerons - Prepare formwork
Details
       

 04-10-2014
4.00
Rearrange tables
Details
     

 04-09-2014
0.60
Firewall - trim front face, redo one bit
Details
       

 04-08-2014
1.50
Firewall pieces - Trim aft face, layup front face
Details
       

 04-06-2014
0.10
Firewall pieces - inspect AFT face #2
Details
     

 04-05-2014
1.30
Firewall pieces - redo aft face
Details
       

 04-04-2014
1.00
Main Landing Gear Bulkheads - Trimmed Front face
Details
     

 04-04-2014
1.00
Firewall pieces - glass aft face
Details
       

 04-03-2014
1.00
Mail Landing Gear Bulkheads - Glass front face. Re
Details
       

 04-02-2014
0.70
Landing Gear Bulkheads - Trim aft face
Details
     

 03-29-2014
2.00
Main Landing Gear Bulkheads - Glass aft
Details
       

 03-28-2014
2.30
Landing Gear Bulkheads - Preparation
Details
       

 03-27-2014
2.20
Instrument Panel - stiffeners
Details
     

 03-26-2014
1.70
Instrument Panel - stiffeners
Details
       

 03-25-2014
1.30
Instrument Panel - stiffeners
Details
       

 03-24-2014
3.80
Instrument Panel - stiffeners. MLG - hard points
Details
       

 03-22-2014
0.30
Instrument Panel - stiffeners. MLG cut out hard po
Details
     

 03-21-2014
0.70
Instrument panel - trim front. Layup MLG hardpoint
Details
       

 03-20-2014
3.30
Instrument Panel - Front fail and redo
Details
       

 03-19-2014
1.50
Instrument Panel - Trimming
Details
     

 03-18-2014
5.30
Instrument Panel - trim rear layup front
Details
       

 03-17-2014
2.30
Instrument Panel - rear face
Details
       

 03-16-2014
0.80
Instrument Panel - smoothing foam joints
Details

 03-15-2014
3.00
Instrument panel - Join foam bits
Details
       

 03-11-2014
3.70
Seatback - layup rear face. Instrument Panel - cut
Details
       

 03-09-2014
2.20
Seatback - trim front, prepare back
Details
       

 03-08-2014
4.30
F22 - finish. Seatback - front face
Details
       

 03-07-2014
2.00
F22 - front face
Details
       

 03-05-2014
1.00
F22 - aft face
Details
       

 03-04-2014
0.80
F22 - preparing fibreglass cloth
Details
     

 03-03-2014
0.80
F22 - prepare foam
Details
       

 03-01-2014
1.00
F28 - Complete. Start F22
Details
       

 02-28-2014
2.00
F28 - front face
Details
       

 02-27-2014
1.00
F28 - rear face
Details
       

 02-26-2014
2.00
F28 bulkhead - preparation
Details
       

 02-06-2014
5.00
Longerons
Details
       

 01-26-2014
1.00
Finish engine mount inserts
Details
       

 01-25-2014
2.00
Firewall hard points
Details

 02-20-2013
2.00
Prepare ply fuselage parts
Details
       

 01-10-2005
1.00
Registered Plans
Details