Brief Description: Construction log analysis, more worktime needed
DId some MSACCESS and Excel analysis tonight. I currently have 314 hours over a period of 18 monthly work periods. Average hours worked on the plane per month is 16 hours, excluding the August-2009 Quickbuild session at Oregon. Doing the math at the current pace it will take me 4 more years assuming a total build of 1,200 hours. Since I want to get this project done wiithin the next 24 months from now I need to put in an average of 40 hours a month or 10 hours a week. That breaks down into one either full day on the wekend or 2-3 hours per nite. A bit sobering but I will start to crank up my activity significantly starting in April.