Date:  12-1-2014
Number of Hours:  1.00
Manual Reference:  
Brief Description:  Third Year Summary

Build start DEC 1 2011 - Today is DEC 1 2014 - Three years building.

This year I completed the CS Spar and in all, 8 spar cap layups were done. Each a huge job. The left and right wings are built although ailerons are yet to be cut out.

I've built the canard and have just begun doing the elevators. A few days on the nose light took place as well.

While it doesn't seem that much I really picked up the pace this year. These planes take a lot of time.

The plan now is to complete the canard, make the winglets then take everything off site and assemble it all at once. Thats going to be a big job. By then I'll need to have my front window removable so I can get the fuselage with spar attached back in.

I'd like to have the basic airframe completed by the end of year 4. Its going to be an adventure.
' style=

CS Spar Done

CS Spar Done

' style=

Wings main section Done

Wings main section Done

' style=

Canard Glassed.

Canard Glassed.

' style=