DOUGs Web Site

Builder:
DOUG WEHRLY
Location:
New Braunfels, TX - USA
Aircraft:
The Airplane Factory - Sling 2
Engine:
Rotax - 912 ULS
Prop:
Warp Drive - 3-Blade, 72" - Fixed
Total Build Time:
576 Hours

March 25, 2018: Project Start

This is my first airplane kit that I have started building. Many moons ago I bought an early Glasair rudder kit and decided very quickly that I'm not into fiberglass, epoxy and micro balloons. Then not too long ago I bought a Sonex Waiex tail kit, and never started on it as I wasn't sure if it was the right plane for me so I sold it.

In 2015 I ran across the TAF Sling while researching kits again and decided that's my kind of airplane so I bought most of the kits for the Sling 2 (minus wings, finishing kits). It sat in the garage for 3 years as life got in the way, but now I am committed to the build and have carved out a big block of time for this project.

My rough plan is to have the plane ready for engine and avionics by May 2019. I'm really enjoying working on this kit.

Recent Activity
 Date Hours Work Log Summary Details
 10-17-2018
1.5
Installed Comm Antenna And Mounting Plates
Details
       

 10-15-2018
0.4
2 - Installed Comm & Nav Coax Connectors
Details
       

 10-15-2018
0.6
1 - Comm Antenna Mount Prep
Details
       

 10-14-2018
0.2
2 - Clecod Booted Flanges To Firewall
Details
       

 10-14-2018
0.5
1 - Clecod Steering Rod Boots To Flanges
Details
       

 10-13-2018
1.0
Installed VOR Antenna BNC Flange Connector
Details
       

 10-12-2018
0.5
BNC Connector Crimping - Practice
Details
       

 10-10-2018
1.0
2 - Completed Heater Flap Assembly
Details
       

 10-10-2018
1.0
1 - Assembled Heater Flap To Hinge
Details
       

 10-09-2018
2.5
Finished Re-mounting Control Linkage
Details
       