Date: 8-12-2007
|
Number of Hours: 1.25
|
Manual Reference: 6W5-2
|
Brief Description: Test nose rib
|
|
Well, I decided to tool up for nose rib production. The first step was to drill the 3/16" tooling hole near the front tip and then run to the hardware store for an appropriate bolt/nut/washer combo. I then carefully marked my first rib (7 left). When I saw that the plans called for a 4mm radius around the front tip, I was skeptical, given my past experience with the horizontal stabilizer nose rib. I decided, however, to give the designer another chance on this part. That was a mistake that will cost me one extra rib. In the "Scratchbuilding Basics" DVD, Mark and David advise that you need to grind it down to 2 or 3mm so you won't have extra material that has no place to go. Seems they were right again! These are not hard parts to make, so after making this adjustment, I expect I'll be able to mark, trim, file, smooth, clamp, bend, drill the lightening hole and flange the hole in under 45 minutes per rib. We shall see.
|
|
Almost perfect
|
|
Too much metal...too little space
|
|
|
|
|
|
|
|
|
Copyright © 2001-2024 Matronics. All Rights Reserved. |