Date:  4-12-2013
Number of Hours:  5.00
Manual Reference:  
Brief Description:  Wiring Day #6

I'm still at it. Not many pictures because its doesn't photo well.

Climbed deep into the tail again today and added two adel clamps to hold the ELT wiring.
Trimmed the GMU44 wries to length and crimped the pins in place. Waiting on a Digi-Key order to arrive with CPC connector. Decided to change the Gmu 44 plugs from M to F as the mounting connector didn't exist for what I had planned. Got it all taken apart and realized (OOPS) this was a factory made plug- oh well there went the warranty. Anyway, it went back together exactly as I needed it for the installation. Testing to follow.

Cleaned up the layers of dust in the tailcone.

Package from Stein arrived, so I was able to exchange the 62 pin plug for a 15 pin plug because the GTX extension only had 13 wires.