Date:  6-25-2022
Number of Hours:  5.00
Manual Reference:  
Brief Description:  C/B bank wiring

I dug into wiring the circuit breaker bank, and by the end of the session, I had 14 of the 20 CBs wired up. I also separated my "power 2" wires and service looped and capped them back down at the root of the wire trunk for future use if needed. They are a secondary source of power, and I likely will never use them. They would be used for the G5, GMC-507, and GTX-45R
' style=

C/B bank progress

C/B bank progress

' style=

service loop of capped wires

service loop of capped wires

' style=

wire cuttings

wire cuttings

' style=