Date:  4-24-2021
Number of Hours:  1.50
Manual Reference:  
Brief Description:  Replace / Upgrade hardware, Cabin Heat Box

I had some misc. parts on order to replace some less-than-optimal hardware and decided to knock that item off the to-do list today. I replaced the AN4-4 bolts that were holding my two regulators in place with 4-5 and now there are 3 threads showing which was better than the 1/2 thread I had showing before. I turned the bolts around as this should be the last time I fiddle with these bolts and now the "more" flush side is in the baggage compartment. I also replaced the two screws on the parking brake valve as they were not long enough.

After that, I installed the cabin heat box with the stainless-steel bolts, washers and nuts - but only after sealing around the pass-thru hole with the supplied Biotherm 100 silicone firestop sealant.
' style=

threads sticking out, turned the bolt arouund too

threads sticking out, turned the bolt arouund too

' style=

PB valve - new hardware

PB valve - new hardware

' style=

cabin heat box installed

cabin heat box installed