03/17/20: 2.87Hrs 1 & 2: F-00055 L&R and F-00074 L&R were riveted to the avionics bay and the firewall respectively.
03/18/20: 0.7Hrs 3: The fasteners were installed in the three free holes on the firewall.
08/11/20 1.4Hrs 4: the end of each rivet and screw were covered with tank seal 5: The main wire harness branches were routed through the slotted holes in the F-00055-L-1 & R-1 support brackets. Secure the wire harness with the snap bushings in the support brackets. 6: The snap bushing was installed in the F-00055-L-1. Then, the FF-1216 pitot line was routed through the snap bushing.