01/10/19: 0.75Hrs 1. The assembly was turned over 2. F-1211 was clecoed to the cone skins.
01/11/19: 4.43Hrs 3. The J-stiffeners were hooked to the frames, then clecoed. 4. A string was routed forward to aft and then returned to the forward end, both ends were taped to the bottom skin. 5. WH-P30-1 was routed through the bushings, the red heatshrink was alligned with the last one.