Date:  1-12-2013
Number of Hours:  5.00
Manual Reference:  
Brief Description:  Pitot, Static, AOA plumbing. D-Sub wiring

Received the parts I needed to do the Pitot, Static, and AOA plumbing. First I installed the male NPT Tee connectors to the Vertical Power GADAHRS, and then the Male NPT 90 degree connectors to the Dynon 201 ADAHRS on top for the Pitot and Static, and then the other 90 degree connector in the Dynon 200 ADAHRS on the bottom for the AOA plumbing. Cut all tubing to size and heated with the heat gun to get the bends without stress for each connection. I then worked on the Pitch Servo wiring by first making the male pin attachments to the wires, putting heat shrink around the wires and and installing in the D-Sub connector and shell. Decided to make the power and ground connections using knife connectors in case I ever wanted to remove anything. Crimped on the knife terminals for each wire on both the servo side and the wiere harness sides and connected. Also put heat shrink over each connection as you can see in picture number 2. Crimped pins on for the female D-Sub connector that goes to the Network Hub from the wiring harness from the Skyview. After making all connections and installing I realized I have a couple of the data pins in the wrong spots in the connectors and will have to rearrange them tomorrow. Note to self---I have the same pining issue with the data wires coming from the Roll Servo in the wing and will have to make the same change.
' style=

Pitot, Static, AOA Plumbing

Pitot, Static, AOA Plumbing

' style=

Pitch Servo Wiring

Pitch Servo Wiring

' style=

Pitch Servo and Netwrok D-Subs

Pitch Servo and Netwrok D-Subs

' style=










Copyright © 2001-2024 Matronics. All Rights Reserved.