Randy's 750 Cruzer Project
CH750 Cruzer
Landing Gear
Work Logs Found:
8
Category Work Time:
16 Hours
Date
Hours
Work Log Summary
Details
11-23-2024
2.00
Safety wired nose strut & nose wheel
05-29-2023
3.00
Installed nosewheel strut and wheel
Details
02-26-2023
2.00
Mounted main tires on rims
Details
02-26-2023
2.00
Installed wheels on main gear
02-26-2023
1.00
Bolted spacer to nose wheel fork
Details
02-12-2023
2.00
Mounted nose wheel tire on rim
Details
01-29-2023
3.00
Installed main gear
Details
01-22-2023
1.00
Trimmed nose gear lower bearing
Details
SITE NAVIGATION
Contact Builder
CH750 Cruzer Home
Category
# Logs
# Hours
All
369
1003
Brakes
4
13
Center Console
2
9
Controls
27
52
Doors
3
11
Elevator
18
44
Empennage
10
25
Engine
9
28
Firewall
10
22
Flaperons
5
11
Fuel System
20
59
Fuselage
103
256
Horizontal Stablizer
24
63
Landing Gear
8
16
Miscellaneous
2
7
None
4
5
Prop
1
2
Rudder
2
8
Seats
6
10
Vertical Stabilizer
9
22
Windshield
4
15
Wings
98
325
Copyright © 2001-2026 Matronics. All Rights Reserved.