Date
|
Hours
|
Work Log Summary

|
Details

|
09-09-2023
|
6.00
|
Installed the emergency canopy eject system
|
Details
|
|
|
09-07-2023
|
7.00
|
Completde buss manager installation and engine mon
|
Details
|
|
|
07-21-2023
|
11.00
|
Installed the control cables
|
Details
|
|
|
06-25-2023
|
4.00
|
Deburred and primed miscelaneous floor panels
|
Details
|
|
|
05-10-2023
|
4.00
|
Cowling test fitting
|
Details
|
|
|
05-09-2023
|
7.50
|
Added rubber sealing strips to intakes on bottom c
|
Details
|
|
|
05-08-2023
|
6.00
|
Added rubber seal strips to the engine baffles
|
Details
|
|
|
05-04-2023
|
7.00
|
Installed air intake snorkle
|
Details
|
|
|
04-28-2023
|
7.00
|
Installed baffle assemblies to the engine
|
Details
|
|
|
04-20-2023
|
7.00
|
Continued assembling the engine baffles
|
Details
|
|
|
04-17-2023
|
2.00
|
Added RTV strips to rear baffle components
|
Details
|
|
|
04-15-2023
|
6.50
|
Started fabriaction of engine baffles
|
Details
|
|
|
04-06-2023
|
5.00
|
Added bottom cowl close-out piece
|
Details
|
|
|
04-01-2023
|
9.50
|
Fabricated the front wheel fairing
|
Details
|
|
|
03-17-2023
|
7.00
|
Added oil access door to top cowling
|
Details
|
|
|
03-09-2023
|
9.00
|
Continued cowling work
|
Details
|
|
|
02-24-2023
|
16.00
|
Continuation of fitting the cowling
|
Details
|
|
|
01-23-2023
|
20.00
|
Fitting the cowling
|
Details
|
|
|
12-01-2022
|
6.50
|
Added items to front of firewall
|
Details
|
|
|
11-03-2022
|
6.00
|
Assembled cooling flap assembly
|
Details
|
|
|
11-01-2022
|
6.00
|
Assembled and attached front landing gear
|
Details
|
|
|
10-14-2022
|
4.00
|
Attached engine mount and cleaned up some wiring.
|
Details
|
|
|
10-08-2022
|
6.00
|
Reinstalled instruments and 1st power test.
|
Details
|
|
|
10-03-2022
|
4.00
|
Started the FlyEFII Bus Manager Installation
|
Details
|
|
|
10-02-2022
|
2.50
|
Fabricated GPS antenna mount doubler
|
Details
|
|
|
10-01-2022
|
60.00
|
Nearly finished with wiring
|
Details
|
|
|
05-31-2022
|
1.00
|
test
|
|
  |
|
05-30-2022
|
12.00
|
Continued landing gear and wheel fairing fitting
|
Details
|
|
|
05-13-2022
|
10.00
|
Started gear and wheel fairing fitting
|
Details
|
|
|
05-05-2022
|
12.00
|
Main Landing gear installation
|
Details
|
|
|
01-10-2022
|
10.00
|
Installing misc avionics components
|
Details
|
|
|
01-07-2022
|
6.00
|
Additional panel work
|
Details
|
|
|
01-03-2022
|
4.00
|
Preliminary seat design
|
Details
|
|
|
12-30-2021
|
9.00
|
Instrument Panel Work
|
Details
|
|
|
10-18-2021
|
12.00
|
Started instrument panel design and fabrication
|
Details
|
|
|
10-16-2021
|
6.00
|
Prepared landing gear components
|
Details
|
|
|
09-27-2021
|
8.00
|
Seat frame assembly and start of top forward skin
|
Details
|
|
|
09-17-2021
|
3.00
|
Final fitting of canopy
|
Details
|
|
|
09-15-2021
|
14.00
|
Finished build up of fiberglass transition of cano
|
Details
|
|
|
08-30-2021
|
4.00
|
Added dyed fiberclass strips to the canopy skin jo
|
Details
|
|
|
08-28-2021
|
4.00
|
Added Epoxy/microballoon filler to canopy/fuse joi
|
Details
|
|
|
08-15-2021
|
6.00
|
Built and mounted fuselage on a rotisserie
|
Details
|
|
|
08-13-2021
|
5.00
|
Assembling and test fitting canopy frame
|
Details
|
|
|
08-06-2021
|
5.00
|
Continued assembly of the canopy frame
|
Details
|
|
|
07-24-2021
|
6.00
|
Putting together the forward part of the canopy fr
|
Details
|
|
|
06-24-2021
|
5.00
|
Preparing parts for forward canopy frame
|
Details
|
|
|
06-21-2021
|
4.00
|
Added access panels for access to subpanel
|
Details
|
|
|
06-19-2021
|
4.00
|
Installed canopy latching mechanism
|
Details
|
|
|
06-18-2021
|
7.00
|
Rear window fitted
|
Details
|
|
|
06-17-2021
|
5.00
|
Added subpanel and main panel assemblies
|
Details
|
|
|
06-15-2021
|
6.00
|
Painted interior, Added pitch AP servo
|
Details
|
|
|
06-02-2021
|
7.00
|
Installed rudder/brake pedals and flap motor
|
Details
|
|
|
05-30-2021
|
9.00
|
Fuel lines in fuselage
|
Details
|
|
|
05-23-2021
|
5.00
|
More soundproofing
|
Details
|
|
|
05-19-2021
|
6.00
|
Added soundproofing and baggage area floor
|
Details
|
|
|
04-11-2021
|
5.00
|
Assembled the roll-over bar
|
Details
|
|
|
04-06-2021
|
7.00
|
Roll over bar prep.
|
Details
|
|
|
03-28-2021
|
5.00
|
Elevator push/pull rods and bellcrank
|
Details
|
|
|
03-26-2021
|
4.00
|
Forward fuselage parts
|
Details
|
|
|
03-16-2021
|
3.00
|
Assembled subpanel components
|
Details
|
|
|
03-08-2021
|
4.00
|
Preparing subpannel parts
|
Details
|
|
|
02-27-2021
|
5.00
|
Fitted firewall insulation and added master cylind
|
Details
|
|
|
02-23-2021
|
2.50
|
Assembled rudder pedals
|
Details
|
|
|
02-21-2021
|
9.00
|
Preparing inner deck and rudder pedal parts
|
Details
|
|
|
02-15-2021
|
6.00
|
Attached empanage to fuselage
|
Details
|
|
|
02-03-2021
|
4.00
|
Preparing to join fuselage to empanage
|
Details
|
|
|
01-23-2021
|
5.00
|
Installed seat back suport rail assembly
|
Details
|
|
|
01-03-2021
|
7.50
|
Riveted right side fuselage skin
|
Details
|
|
|
12-20-2020
|
7.00
|
Prepared the right side fuselage skin
|
Details
|
|
|
12-06-2020
|
8.00
|
Riveted left side fuselage skin
|
Details
|
|
|
11-28-2020
|
6.00
|
Continued preparing fuselage parts that attach to
|
Details
|
|
|
11-24-2020
|
5.00
|
Preparing left side fuselage skin and components
|
Details
|
|
|
11-19-2020
|
4.00
|
Preparing for side skin attach
|
Details
|
|
|
11-17-2020
|
4.00
|
Prepared upper and lower longerons
|
Details
|
|
|
11-08-2020
|
7.00
|
Connecting mid fuselage to firewall section
|
Details
|
|
|
10-23-2020
|
6.00
|
Joined 2 parts of lower fuselage
|
Details
|
|
|
10-11-2020
|
5.00
|
Finished firewall section of the plans...
|
Details
|
|
|
10-09-2020
|
3.00
|
Forward bottom fuselage
|
Details
|
|
|
10-05-2020
|
7.00
|
Firewall continued
|
Details
|
|
|
10-03-2020
|
4.00
|
Firewall continued
|
Details
|
|
|
10-01-2020
|
2.50
|
Firewall continued
|
Details
|
|
|
09-29-2020
|
3.00
|
Firewall continued
|
Details
|
|
|
09-27-2020
|
5.00
|
More firewall parts
|
Details
|
|
|
09-25-2020
|
3.50
|
Prepared parts for the firewall tunnel assembly
|
Details
|
|
|
09-24-2020
|
5.00
|
Firewall Parts prepped and assembed
|
Details
|
|
|
09-21-2020
|
3.50
|
Mid fuse bottom skin is on
|
Details
|
|
|
09-11-2020
|
1.50
|
Mid fuselage continued
|
Details
|
|
|
09-10-2020
|
1.50
|
Mid fuselage continued
|
Details
|
|
|
09-09-2020
|
5.00
|
Mid fuselage continued
|
Details
|
|
|
09-05-2020
|
3.00
|
Mid fuselage continued
|
Details
|
|
|
08-29-2020
|
3.50
|
Continued mid fuselage assembly
|
Details
|
|
|
08-26-2020
|
3.00
|
Continued mid fuselage assembly
|
Details
|
|
|
08-22-2020
|
4.50
|
Prepared parts for the deck of the main seating ar
|
Details
|
|
|
08-20-2020
|
4.00
|
Mid fuselage deck components
|
Details
|
|
|
08-15-2020
|
4.50
|
Forward Mid Fuselage Bulkheads continued
|
Details
|
|
|
08-09-2020
|
4.00
|
Forward Mid Fuselage Bulkheads
|
Details
|
|
|
08-01-2020
|
4.50
|
Started fuselage assembly
|
Details
|
|