Work Logs Found: 97
Category Work Time: 626 Hours
 Date
Hours
Work Log Summary

Details

 09-09-2023
6.00
Installed the emergency canopy eject system
Details
       

 09-07-2023
7.00
Completde buss manager installation and engine mon
Details
       

 07-21-2023
11.00
Installed the control cables
Details
       

 06-25-2023
4.00
Deburred and primed miscelaneous floor panels
Details
       

 05-10-2023
4.00
Cowling test fitting
Details
       

 05-09-2023
7.50
Added rubber sealing strips to intakes on bottom c
Details
       

 05-08-2023
6.00
Added rubber seal strips to the engine baffles
Details
       

 05-04-2023
7.00
Installed air intake snorkle
Details
       

 04-28-2023
7.00
Installed baffle assemblies to the engine
Details
       

 04-20-2023
7.00
Continued assembling the engine baffles
Details
       

 04-17-2023
2.00
Added RTV strips to rear baffle components
Details
       

 04-15-2023
6.50
Started fabriaction of engine baffles
Details
       

 04-06-2023
5.00
Added bottom cowl close-out piece
Details
       

 04-01-2023
9.50
Fabricated the front wheel fairing
Details
       

 03-17-2023
7.00
Added oil access door to top cowling
Details
       

 03-09-2023
9.00
Continued cowling work
Details
       

 02-24-2023
16.00
Continuation of fitting the cowling
Details
       

 01-23-2023
20.00
Fitting the cowling
Details
       

 12-01-2022
6.50
Added items to front of firewall
Details
       

 11-03-2022
6.00
Assembled cooling flap assembly
Details
       

 11-01-2022
6.00
Assembled and attached front landing gear
Details
       

 10-14-2022
4.00
Attached engine mount and cleaned up some wiring.
Details
       

 10-08-2022
6.00
Reinstalled instruments and 1st power test.
Details
       

 10-03-2022
4.00
Started the FlyEFII Bus Manager Installation
Details
       

 10-02-2022
2.50
Fabricated GPS antenna mount doubler
Details
       

 10-01-2022
60.00
Nearly finished with wiring
Details
       

 05-31-2022
1.00
test

 05-30-2022
12.00
Continued landing gear and wheel fairing fitting
Details
       

 05-13-2022
10.00
Started gear and wheel fairing fitting
Details
       

 05-05-2022
12.00
Main Landing gear installation
Details
       

 01-10-2022
10.00
Installing misc avionics components
Details
       

 01-07-2022
6.00
Additional panel work
Details
       

 01-03-2022
4.00
Preliminary seat design
Details
       

 12-30-2021
9.00
Instrument Panel Work
Details
       

 10-18-2021
12.00
Started instrument panel design and fabrication
Details
       

 10-16-2021
6.00
Prepared landing gear components
Details
       

 09-27-2021
8.00
Seat frame assembly and start of top forward skin
Details
       

 09-17-2021
3.00
Final fitting of canopy
Details
       

 09-15-2021
14.00
Finished build up of fiberglass transition of cano
Details
       

 08-30-2021
4.00
Added dyed fiberclass strips to the canopy skin jo
Details
       

 08-28-2021
4.00
Added Epoxy/microballoon filler to canopy/fuse joi
Details
       

 08-15-2021
6.00
Built and mounted fuselage on a rotisserie
Details
       

 08-13-2021
5.00
Assembling and test fitting canopy frame
Details
       

 08-06-2021
5.00
Continued assembly of the canopy frame
Details
       

 07-24-2021
6.00
Putting together the forward part of the canopy fr
Details
       

 06-24-2021
5.00
Preparing parts for forward canopy frame
Details
       

 06-21-2021
4.00
Added access panels for access to subpanel
Details
       

 06-19-2021
4.00
Installed canopy latching mechanism
Details
       

 06-18-2021
7.00
Rear window fitted
Details
       

 06-17-2021
5.00
Added subpanel and main panel assemblies
Details
       

 06-15-2021
6.00
Painted interior, Added pitch AP servo
Details
       

 06-02-2021
7.00
Installed rudder/brake pedals and flap motor
Details
       

 05-30-2021
9.00
Fuel lines in fuselage
Details
       

 05-23-2021
5.00
More soundproofing
Details
       

 05-19-2021
6.00
Added soundproofing and baggage area floor
Details
       

 04-11-2021
5.00
Assembled the roll-over bar
Details
       

 04-06-2021
7.00
Roll over bar prep.
Details
       

 03-28-2021
5.00
Elevator push/pull rods and bellcrank
Details
       

 03-26-2021
4.00
Forward fuselage parts
Details
       

 03-16-2021
3.00
Assembled subpanel components
Details
       

 03-08-2021
4.00
Preparing subpannel parts
Details
       

 02-27-2021
5.00
Fitted firewall insulation and added master cylind
Details
       

 02-23-2021
2.50
Assembled rudder pedals
Details
       

 02-21-2021
9.00
Preparing inner deck and rudder pedal parts
Details
       

 02-15-2021
6.00
Attached empanage to fuselage
Details
       

 02-03-2021
4.00
Preparing to join fuselage to empanage
Details
       

 01-23-2021
5.00
Installed seat back suport rail assembly
Details
       

 01-03-2021
7.50
Riveted right side fuselage skin
Details
       

 12-20-2020
7.00
Prepared the right side fuselage skin
Details
       

 12-06-2020
8.00
Riveted left side fuselage skin
Details
       

 11-28-2020
6.00
Continued preparing fuselage parts that attach to
Details
       

 11-24-2020
5.00
Preparing left side fuselage skin and components
Details
       

 11-19-2020
4.00
Preparing for side skin attach
Details
       

 11-17-2020
4.00
Prepared upper and lower longerons
Details
       

 11-08-2020
7.00
Connecting mid fuselage to firewall section
Details
       

 10-23-2020
6.00
Joined 2 parts of lower fuselage
Details
       

 10-11-2020
5.00
Finished firewall section of the plans...
Details
       

 10-09-2020
3.00
Forward bottom fuselage
Details
       

 10-05-2020
7.00
Firewall continued
Details
       

 10-03-2020
4.00
Firewall continued
Details
       

 10-01-2020
2.50
Firewall continued
Details
       

 09-29-2020
3.00
Firewall continued
Details
       

 09-27-2020
5.00
More firewall parts
Details
       

 09-25-2020
3.50
Prepared parts for the firewall tunnel assembly
Details
       

 09-24-2020
5.00
Firewall Parts prepped and assembed
Details
       

 09-21-2020
3.50
Mid fuse bottom skin is on
Details
       

 09-11-2020
1.50
Mid fuselage continued
Details
       

 09-10-2020
1.50
Mid fuselage continued
Details
       

 09-09-2020
5.00
Mid fuselage continued
Details
       

 09-05-2020
3.00
Mid fuselage continued
Details
       

 08-29-2020
3.50
Continued mid fuselage assembly
Details
       

 08-26-2020
3.00
Continued mid fuselage assembly
Details
       

 08-22-2020
4.50
Prepared parts for the deck of the main seating ar
Details
       

 08-20-2020
4.00
Mid fuselage deck components
Details
       

 08-15-2020
4.50
Forward Mid Fuselage Bulkheads continued
Details
       

 08-09-2020
4.00
Forward Mid Fuselage Bulkheads
Details
       

 08-01-2020
4.50
Started fuselage assembly
Details
       