Date:  5-10-2019
Number of Hours:  13.50
Manual Reference:  
Brief Description:  39iS/U-16, 39iS/U-17, 42MiS/U-08, 42MiS/U-09, 42Mi

42MiS/U-08:
The spar pin switch was installed.
The bushings called out in step 9 were installed except one we're missing and it has been ordered.
9:00 - 9:20 42-08 step 8

9:20 - 42-09 all
42MiS/U-09:
All of the steps were completeted.
The circumference around the aftmost hole for the switch was sanded to remove paint and primer.

42MiS/U-10:
ES-00301 was riveted to to F-01203A-1.

42MiS/U-12:
We started routing the main harness almost completing step 1, there are two screws that cannot be installed since there are no standoffs on the other side and the manual doesn't call out for nuts.

The canopy fairing is still being sanded and filled with bubbles.