Team: Alvaro Lopez, Juan Isiordia, Angel Rodriguez Abscent:0
Today we continued with the step 6, we placed 4 POP rivets and began installing the 28 rivets AN470AD4-9 that attach the flange of the pieces F-01224-L-1 & R-1 to the bulkhead.
Note 1.- the team placed 5 rivets incorrectly because at the end of the installation we noticed that there were gaps between the parts and the rivet. Note 2.- the team made a mistake, we realized that we had taken a step, that is, to place a rivet in the piece F-01204D to F-01204 that afterwards we could not place. Therefore, this step is impossible due to the rivet located under the flange of part F-01224-L-1. Therefore, we need to remove a minimum of 4 to 8 rivets and reinstall them.