Date:  7-26-2009
Number of Hours:  5.00
Manual Reference:  Section 25-6
Brief Description:  Section 25-6, Steps 1 to 7 Riveting the Aft Bulkhe

Section 25-6, Steps 1 to 7 Riveting the Aft Bulkhead assembly. Step 1 to 7, I followed the instruction and riveted the Aft Bulkhead Assembly as shown in Figure 1. Step 2, Then after locating the correct AN-3 bolts Nuts and Washers I bolted all the correct hardware to the Aft Bulkhead Assembly as shown in Figure 2. Then checked that all were properly torque with-in specification 25 in/lbs. Step 4, Then inserted the 4 3/4 inch snap BushingsSB750-10 into the holes I drilled with the Unibit into the Center Section Bulkheads F-1004F-L/R. Step 5 to 7, I created a small Teflon Wear Strip F-1004M from a 1/8 thick by 1/2 inch wide and 4 and 3/4 inch UHMW plastic strip and riveted to the center top of the F-1004B Center Section Bulkhead. Time about 5 hours
' style=

Teflon Wear Strip F-1004M from a 1/8 thick by 1/2 inch wide and 4 and 3/4 inch UHMW plastic strip

Teflon Wear Strip F-1004M from a 1/8 thick by 1/2 inch wide and 4 and 3/4 inch UHMW plastic strip

' style=










Copyright © 2001-2024 Matronics. All Rights Reserved.