Date:  5-25-2013
Number of Hours:  5.00
Manual Reference:  49-06 to 49-11
Brief Description:  Installed overflow bottle and began working on coo

Needed to re-seal the cooler door with RTV sealant. Opened it before the silicone set up from yesterday. Insatlled the overflow bottle to firewall per plans.

Began working ahead in plans. Added grommet to firewall for the control cables. Pulled all the hardware that I'll need for the cooler door cable install.

Began working on the oil cooler frame parts. Deburred, countersunk a few spots and primed the parts.
' style=

Installed coolant overflow bottle with hose install.  Note red painted band.

Installed coolant overflow bottle with hose install. Note red painted band.

' style=

Oil cooler frame parts were primed

Oil cooler frame parts were primed