Andrew's RV10
RV-10
All
Work Logs Found:
236
Category Work Time:
1792 Hours
Date
Hours
Work Log Summary
Details
04-25-2017
3.00
Weight & Balance
Details
04-23-2017
8.00
Final panel & avionics installation
Details
04-19-2017
1.00
Transition Training
Details
04-18-2017
1.00
Transition Training
Details
04-13-2017
24.00
Panel Paint and engraving
Details
04-07-2017
1.00
SB 16-03-28 compliance
Details
04-07-2017
1.00
SB 16-03-28 Compliance
Details
03-31-2017
3.00
Rear Seat interior
Details
03-19-2017
5.00
Panel prep for paint
Details
03-17-2017
6.00
Fuel Qty Calibration
Details
03-14-2017
2.00
ELT Registration
Details
03-10-2017
6.00
Avionics Calibration
Details
03-10-2017
1.00
Avionics Calibration
Details
03-07-2017
3.00
Magnetometer Calibration
03-03-2017
5.00
First Engine Run
Details
03-02-2017
3.00
Priming Oil Lines
Details
02-24-2017
15.00
Fitting gear fairings to plane
Details
02-17-2017
2.00
ADAHRS Calibration
Details
02-15-2017
20.00
Avionics configuring
Details
02-11-2017
10.00
Avionics smoke test
Details
02-05-2017
3.00
FLYLEDs Final install
Details
02-04-2017
4.00
Aileron Trim
Details
01-28-2017
4.00
OAT Probe
Details
01-24-2017
12.00
Wing Wire Runs
01-21-2017
10.00
Final wing install
Details
01-20-2017
2.00
Moving to the Airport
Details
01-20-2017
1.00
Moving to the Airport
Details
01-20-2017
8.00
Intitial wing fit
Details
01-16-2017
4.00
Wing Root Fairing
Details
01-14-2017
6.00
Control Stick wires
Details
01-09-2017
1.00
NACA air vent
Details
01-06-2017
8.00
Engine wire runs
Details
01-02-2017
3.00
POS-12 wire connection
Details
01-02-2017
4.00
ELT solder connector
Details
01-01-2017
10.00
Wire runs
Details
12-30-2016
8.00
Wire Runs
Details
12-29-2016
6.00
Headset jacks
Details
12-28-2016
1.00
Mouse
Details
12-26-2016
3.00
Pitch Trim D-Sub
Details
12-23-2016
3.00
FLYLEDS circuit board D-Sub
Details
12-20-2016
10.00
Audio Wires
Details
12-16-2016
8.00
More wire runs
Details
12-11-2016
4.00
Passenger Door Lock
Details
12-10-2016
8.00
Panel wire runs
Details
12-10-2016
1.00
FAB top plate
Details
12-07-2016
6.00
cowl baffle seal
Details
12-04-2016
3.00
Cup holder and side pocket
Details
12-04-2016
2.00
Bleeding Brakes
Details
11-30-2016
5.00
Cowl cosmetics
Details
11-27-2016
2.00
FAB baffle seal
11-27-2016
3.00
Exhaust
Details
11-26-2016
2.00
Cowl repair
Details
11-26-2016
4.00
Cowl Air Inlet
Details
11-23-2016
4.00
Exhaust
Details
11-21-2016
6.00
Cowl air inlet
11-20-2016
1.00
Cylinder fin crack
Details
11-19-2016
15.00
FAB construction
Details
11-07-2016
6.00
Prop Cable problem
Details
11-05-2016
8.00
Shunts, starter, battery, alternator cables
Details
10-30-2016
13.00
Baffle seals
Details
10-28-2016
6.00
Cowl fit
Details
10-25-2016
8.00
Windshield Fairing
Details
10-24-2016
1.00
Windshield Fairing
Details
10-24-2016
2.00
Control sticks
Details
10-23-2016
10.00
Windshield fairing
Details
10-22-2016
3.00
Windshield fairing
Details
10-22-2016
10.00
Engine Baffle
10-21-2016
4.00
Window prep for fiberglass
Details
10-20-2016
3.00
Baffle work
Details
10-15-2016
8.00
Baffle work
Details
10-14-2016
4.00
Louvers
10-14-2016
10.00
Engine Baffle
10-11-2016
4.00
Cowl Fit
Details
10-06-2016
2.00
Air inlet ramps
Details
10-02-2016
6.00
windshield install
10-02-2016
10.00
Window install
Details
09-26-2016
10.00
Cowl Fit
Details
09-25-2016
3.00
Cowl Fit
09-24-2016
2.00
GPS and Dome light pass-thrus
Details
09-22-2016
1.00
Panel structure install
Details
09-21-2016
3.00
Misc. panel installations
Details
09-21-2016
1.00
Firewall insulation
Details
09-19-2016
1.00
N Number
Details
09-17-2016
3.00
Rear window fit
Details
09-15-2016
8.00
Aerosport Interior side panels
09-12-2016
8.00
Initial nose gear fairing work
09-04-2016
10.00
More interior paint
Details
09-03-2016
10.00
More interior paint
09-03-2016
6.00
Door Paint
Details
08-26-2016
1.00
Panel wiring
Details
08-26-2016
1.00
FAA Registration
Details
08-19-2016
10.00
Spinner completion
Details
08-18-2016
10.00
Spinner work
Details
08-15-2016
4.00
Registration
Details
08-14-2016
10.00
Magnetometor
Details
08-13-2016
3.00
Pitch A/P servo install
Details
08-07-2016
6.00
B&C Standby alternator
Details
08-06-2016
4.00
Aerosport console fit
Details
08-04-2016
10.00
Empennage Fairing
Details
07-08-2016
4.00
Rudder fairing
07-08-2016
10.00
Elevator / H.S. Fairings
07-06-2016
3.00
Fitting FLYLEDs to wingtip
06-28-2016
10.00
Tailcone Avionics Shelf
Details
06-28-2016
1.00
Carpet
Details
06-27-2016
4.00
Seats
Details
06-25-2016
2.00
FLYLEDS testing
06-24-2016
2.00
FLYLEDS kit cont'd
06-24-2016
2.00
FLYLEDS kit (cont'd)
06-24-2016
4.00
FLYLEDS kit
Details
06-12-2016
10.00
Elevator rework cont'd
Details
06-07-2016
15.00
Nav antenna
Details
06-05-2016
20.00
Elevator counter balance rework
Details
05-29-2016
30.00
Garmin modules
Details
05-22-2016
20.00
V.S. Rebuild
Details
05-20-2016
6.00
H.S. attach
Details
05-18-2016
30.00
Completed new Horizontal Stab
Details
05-10-2016
3.00
Avionics and panel Arrived
Details
05-05-2016
15.00
New Horizontal Stab
Details
05-01-2016
4.00
Hanging the prop
04-24-2016
4.00
B&C 60 amp primary alternator
04-08-2016
6.00
Hanging the engine
04-03-2016
10.00
Spinner fit
Details
04-02-2016
6.00
Cabin Top final install
Details
04-01-2016
40.00
Cabin top interior
Details
03-27-2016
10.00
Engine mount install
Details
03-25-2016
8.00
Matco Wheel assy
Details
03-25-2016
15.00
Interior Paint
Details
03-15-2016
1.00
Hartzell Prop arrives
Details
03-08-2016
10.00
Aerosport Overhead Console
Details
03-05-2016
10.00
Aerosport Overhead Console
Details
02-29-2016
10.00
McMaster Door Seal
Details
02-28-2016
20.00
Door handle/ plane around 3rd latch
Details
02-20-2016
8.00
Door Buildup
Details
02-14-2016
2.00
Door Buildup
Details
02-13-2016
10.00
Door Buildup
02-12-2016
10.00
Door Buildup
Details
02-12-2016
3.00
Door Buildup
Details
02-06-2016
3.00
Door Buildup
Details
02-05-2016
6.00
Finish Kit / FWF kit
Details
01-31-2016
1.00
Engine Arrival
Details
01-18-2016
8.00
Aerosport overhead
Details
01-10-2016
20.00
Initial drilling cabin top
Details
01-08-2016
20.00
Cabin top initial fit
Details
01-05-2016
12.00
fitted control sticks
12-20-2015
10.00
Fuel system
Details
12-19-2015
5.00
Parking brake
Details
12-18-2015
10.00
Brake system
12-13-2015
8.00
back floorboards
12-12-2015
2.00
Comm coax run
Details
12-11-2015
10.00
Comm antennas
Details
12-08-2015
15.00
Baggage floors
Details
12-04-2015
8.00
Fuselage cradle
Details
11-29-2015
10.00
Landing gear mounts
Details
11-28-2015
5.00
Insulated fwd floorboards
Details
11-15-2015
4.00
Riveting tailcone mate
Details
11-14-2015
8.00
Mating/match drilling tailcone
Details
11-09-2015
2.00
Riveted fwd seat pans
11-07-2015
10.00
Fuselage skin riveting
Details
11-06-2015
6.00
Engine mount gussets
Details
10-10-2015
10.00
Longeron/Skin Drillout
10-01-2015
10.00
FWD Side Skin Bending
09-26-2015
10.00
Aft Side Skin Drillout
09-18-2015
10.00
Bending Aft Side Skins
09-13-2015
15.00
Bending Longerons cont'd
09-07-2015
15.00
Bending Longerons
Details
08-21-2015
10.00
Landing gear tower
Details
08-20-2015
4.00
Landing gear tower
Details
08-14-2015
6.00
Riveting FWD/Mid fuse
Details
08-03-2015
6.00
FWD fuse / Mid fuse
Details
07-14-2015
4.00
FWD fuselage Bottom Skins continued
Details
07-13-2015
4.00
FWD fuselage Bottom Skins cont'd
07-12-2015
4.00
FWD fuselage Bottom Skins
Details
06-03-2015
3.00
Step Mount Bracket
Details
06-03-2015
10.00
Riveting the Mid Fuselage
05-31-2015
4.00
Airward Tunnel Access Cover
Details
05-22-2015
10.00
Firewall buildup
Details
05-08-2015
10.00
Baggage ribs and Belly Skin
04-19-2015
10.00
Mid Fuse Bulkhead Assy
03-24-2015
10.00
Priming parts
Details
03-06-2015
10.00
Wing tips
Details
01-30-2015
10.00
Center Section Bulkhead
Details
08-01-2014
0.00
Factory Construction
Details
03-22-2014
15.00
Rivet Wing Skins
Details
03-22-2014
2.00
Completed Wing Skin pictures
03-21-2014
2.00
Gretz Pitot Mast doubler / cut-out
Details
03-21-2014
2.00
Gretz Pitot Mast doubler / cut-out
03-14-2014
7.00
Aileron Push Tubes
Details
02-17-2014
4.00
Deburr, Dimple and Prime Lower Wing Skinks
02-07-2014
3.00
Final Drilling Lower Wing Skins
01-10-2014
10.00
Installing Duckworks Leading Edge Kit
Details
01-10-2014
1.00
Duckworks cont'd
Details
01-10-2014
1.00
Duckworks cont'd
Details
01-10-2014
1.00
Duckworks cont'd
Details
01-07-2014
1.00
Duckworks LED Leading Edge Light Kit
Details
12-23-2013
3.00
fuel sending unit and leak testing
Details
11-26-2013
5.00
Flap and Aileron gap farings
11-26-2013
2.00
Flap and Aileron gap fairings
11-15-2013
4.00
Wiring Conduit
Details
10-19-2013
5.00
Fuel Sending Units
Details
09-27-2013
3.00
Drilling Elevator Control Horns
09-26-2013
3.00
Attaching Right Elevator
09-25-2013
3.00
Attaching left elevator
09-01-2013
0.00
Commercial Certificate
Details
07-03-2013
1.00
Seatbelt brackets installed
07-02-2013
4.00
Riveting Tailcone
07-01-2013
1.00
Static Port installation
Details
07-01-2013
10.00
Riveting Tailcone
07-01-2013
10.00
Riveting Tailcone
07-01-2013
10.00
Riveting Tailcone
07-01-2013
10.00
Riveting Tailcone
06-30-2013
2.00
Riveting Tailcone
05-01-2013
53.00
Deburr/Dimple/Prime all T/C parts/skins
04-22-2013
1.00
Rivet Rudder Trailing Edge
Details
04-08-2013
7.00
Aft Deck Initial Assy & Shoulder Harness Mount
03-23-2013
13.50
Tailcone Initial Assy. Top Skins
03-17-2013
8.00
Tailcone Initial Assy. Skins/Stringers
03-16-2013
6.00
Rolling Elevator Leading Edge
03-16-2013
2.00
Riveting Elevator Trailing Edge
03-15-2013
5.00
Wing Cradle Construction
Details
03-14-2013
1.00
Quickbuild wings arrived
Details
03-08-2013
5.00
Sealing Ribs/Trailing edge Elevator & Trim Tabs
03-06-2013
1.50
Making the F-1032 Longerons
03-04-2013
3.00
Trailing Edge Proseal Jig
03-03-2013
2.50
Priming trim tabs
03-02-2013
2.50
Making the tailcone Stringers
02-25-2013
19.50
Closing up Elevators
02-23-2013
12.00
Tailcone Initial Assy: Bulkhead Components
02-20-2013
11.50
Riveting Parts to the Elevator Skins
02-19-2013
2.00
Riveting Fwd Spar, Doublers, Control horns
02-10-2013
6.50
Riveting Elevator Tip Ribs
02-06-2013
9.50
Elevator Trim Tabs
Details
01-27-2013
23.50
Priming
01-15-2013
27.00
Dimpling Elevator Parts
Details
12-28-2012
15.00
Elevator Initial Assembly
Details
12-18-2012
130.00
Previous Builder's Work
Details
12-04-2012
5.00
Preparing
Details
SITE NAVIGATION
Contact Builder
RV-10 Home
Category
# Logs
# Hours
All
281
2095
Avionics
18
146
Avionics/Electrical
18
146
Avionics/Electrical
27
158
Cabin Top
6
74
Cowl
11
52
Doors
10
76
Electrical
27
158
Empennage
39
534
Engine
17
101
Final Assembly
2
18
Fuel Tanks
2
8
Fuselage
40
302
Gear Fairings
2
23
Interior
11
99
Miscellaneous
9
19
Prop
5
35
Shop Supplies
2
5
Tailcone Attach
3
9
Travel
2
2
Windows
8
45
Wings
22
85