Welcome to my Bearhawk building/logging Web site. Here I will cronicle my adventures scratch building a Bearhawk designed by Bob Barrows. Actually, most of it may be quite boring because I am using it for my building log and will have an entry for each time I work on it. My "goal" is to have it finished by the time my oldest son graduates from high school...AKA my 14 year building plan. I've got 8 years to go. I like to call it my Erbman timeline.

Recent Activity
First Photo
Date

Work Log Summary

02-22-2012
Installed left tank, made cradle.
02-06-2012
Cut out the stiffeners and pocket covers.
The last few rivets in the right rear spar
01-17-2012
Finished riveting the right wing skin.
01-14-2012
More riveting
01-10-2012
Riveting the right bottom skin.
01-03-2012
Riveting on the right wing.
(almost) finished left bottom skin
01-02-2012
Riveting left bottom skin.
12-31-2011
rivet squeezing.
12-07-2011
Left bottom side main spar rivets.
11-29-2011
Finished top skins and installed bottom skins
10-25-2011
More riveting.
10-11-2011
riveting, lots of riveting
07-19-2011
Finished riveting the right bottom nose skin.
07-18-2011
Began riveting the right bottom nose skin.
07-01-2011
Finished riveting the right top nose skin.
06-22-2011
Riveting right top nose skin.
06-19-2011
Riveting bottom skin, D cell.
05-03-2011
Began riveting skins!
02-28-2011
installed 3rd and 4th right skins, prepped 5th.
Priming the right skins
02-26-2011
Installed first 2 skins and primed two more.
02-19-2011
dimpling and priming.
02-16-2011
Dimple and prep...
02-14-2011
finished prepping 4th right skin.
02-13-2011
Work on the 3rd and 4th right wing skin.
02-12-2011
Prepping the 3rd right skin.