| Date: |
7-11-2016 |
|
| Number of Hours: |
6.00 |
|
| Brief Description: |
Start of the Build |
|
|
Finally ready to start building, I had in previous weeks built a 4x4 foot workbench and the build offically started July 11, 2016 at 12:10PM. I followed the instructions from the Zenith Plans. Step one: used a file on all the edges to remove any burs from the CNC machine Step two: Trimmed the Spar Doubler to match the bottom of the spar, used snips to cut and metal file to deburr the rough edges. Step3: label the rib stations on the spar. Step 4: Clamped the doublers onto the spar using handi clamps and drilled through predrilled holes on the spar into the doublers. Clecoed into place. Step 5: Clecoed the rudder horn and drilled out #30 then onto #20 holes. Step 6: Deburred all holes drilled both sides, each part. Step 7: Drilled each rib to final size into the spar and deburred. |
||