| Date: |
9-5-2011 |
|
| Number of Hours: |
3.00 |
|
| Brief Description: |
18 Aft tailcone completion |
|
|
- Updrilled all the holes for the forward attach brackets at the top of the fuselage (photo #1). - Installed 4 AN bolts (2 per side) -- (photo #2). The nuts are located inside the cross tie box and were bear to get in place and to tighten and torque. The plans called for a total of 2 washers on each bolt, but I needed 3 total (one on top; 2 underneath), otherwise the nut was grounding itself on the shank. - Installed the cross tie box support brackets (in progress, photo #3). All of this took time because of assembly, disassembly, deburring, and reassembly. But this completes Sheet F21 for the Tail Cone Box. |
||