Date:    7-23-2011
Number of Hours:    10.00
Brief Description:    Summary so far...........
Empenage components just about complete.
Lower surfaces skins are riveted and ready for inspection.
Quite happy with the flattness of surfaces - not many waves / lumps or bumps - I have not been in a hurry, and taken it fairly slowly. I have logged 66 hours so far, but probably a bit more to be truthful!

Ordered the wings, but with the Sling 4 trying to get to the sky for Oskosh and round the world trip, as well as the metal workers strike, the factory is a little behind on orders.

Will be away for about 10 days, hopefully will be ready by the time I get back
.
I will have to make up a wall bracket to store all the hard work out of harms way.