| Date: |
9-5-2011 |
|
| Number of Hours: |
6.10 |
|
| Brief Description: |
Installed Fuselage Skin |
|
|
Installed and riveted nutplates on bottom fuselage skin, including optional comm antenna. Installed and riveted bottom fuselage skin, including stiffeners and doublers (page 21-16, steps 2, and 4 through 7). Page 21-16 is complete Made step attach angles and match drilled to F-1202F bulkhead (page 21-17, steps 1 through 10 except for step 9). Will seal the step openings with fuel tank sealant once I order some. Match drilled nutplate brackets to F-1202F bulkhead and step angles and installed nutplates (page 21-18, steps 1 through 3). Dimpled step floors and baggage bulkhead. Also, match drilled facet pump bracket and machine countersunk rivet attach holes (page 21-19, steps 1, 5, and 9). Separated autopilot servo brackets and servo angles (page 39-03, steps 1 and 2). Page 39-03 is complete. Finished deburring remaining parts for Section 21. Ready to prep and prime. |
||