Date:    3-7-2016
Number of Hours:    2.00
Brief Description:    Fuselage - Firewall and L/G Box assy
On that day, I finalized Firewall assembly by adding two nutplates, then installing the F801L parts to from face of firewall.

I then moved to assembling the right hand L/G box by riveting the angles to it. I cleco the same angles to the LH L/G box following that

I worked from 15h45 until 18h00, then from 20h00 until 22h00