Brief Description: Prepped airplane to get ready to work
Relocated airplane back in garage.
Stripped off shrink wrap, and generally cleaned up workshop to prep work area to get restarted.
Short term, I amd going to install some LED lights that will be under the dash and illuminate the footwells
Once that's done, I need to debur, prime and dimple the font top deck piece for riveting.
Once the top deck is on, there are only three major tasks left to complete in the garage:
1. Need to install the windscreen and canopy - my guess is this will be about 5 weeks 2. Need to install the engine, controls and accessories - again 5-6 weeks 3. Lastly need to install cowling and accessories- another month
If I can stay on track, I should be looking to take the whole thing to the airport at the end of the summer.