' style=
Date:  4-2-2021
Number of Hours:  3.50
Manual Reference:  
Brief Description:  Install Static Line and Modify Right Sub-panel

Now that the week of family is over, I put in a work session. I decided it was time to finish getting the static line completed and got it routed. Then I installed some nylon ties that would support and hold the line in place. For good measure I wrapped the area where the ties were with silicone tape to give it a little more cushioning and protection.

I routed and secured the line along the longeron and then attached the static line to the "T" that ties in the custom made static ports.

After the line was complete, I decided to mark and make clearance on my right sub panel where the post light wiring would be passing through. Since there would be no static line going through also on the right side I was able to make the clearance smaller.

Felt good to get back working on the project.
' style=

Line attached to port

Line attached to port "T"

' style=

Installed mounts for securing line

Installed mounts for securing line

' style=

Modify Right subpanel for wire pass thru

Modify Right subpanel for wire pass thru

' style=