Steve & Nancy Riffe
|
Date: 4-21-2016
|
Number of Hours: 4.00
|
Manual Reference:
|
Brief Description: Snorkel and #2 baffle work-5
|
|
I finished up reaming all holes to #30, and completed all drilling c/s for nutplate mounting. I was able to remove the #2 baffle as a unit without much issue, so on to riveting. I did the edge finish thing, deburred all holes, cleaned up, scotchbrited, wiped with MEK and shot a coat of primer on all parts. While the primer was drying, I mixed up a batch of resin with flox and glued in one of the air ramps to the upper cowling. I also filled in some holes in the snorkel that had been incorrectly drilled. After the primer had dried, I began riveting the parts that make up the #2 baffle assembly. So far, I was able to use the pneumatic squeezer for all of the rivets on this assembly, but I see a couple that I’ll probably have to shoot with the gun.
|
|
Left air ramp glassed to upper cowl
|
|
Riveting #2 baffles
|
|
More riveting
|
|
|
|
|
|
|
|
|