6/1/19 2.8 Hours Joined wires for strobe/nav lights with #6 eye conectors that connect to power panel . Checked for circuit opens and shorts with ohm meter.
6/2/19 5.0 Hours Worked on upper left and right corners of windshield. Started attaching wires to power panel including adding #6 eye connectors to some wires (most were done before). Will do a smoke test in next day or so.
6/3/19 2.9 Hours Continued with wiring. Made power and ground leads for flap switch. Verified flap operation with power supply conected. Had to re-organize some wires on back of power panel to alow it to slide into instrument panel. Connected power supply to battery side of master solenoid and tried master switch and again flaps. Installed Dynon HDX and powered-up. Smoke test a success! Will do some basic configuring tomorrow and pull plane out of hangar to see if GPS is working.