Date:  10-17-2020
Number of Hours:  4.00
Manual Reference:  
Brief Description:  Wing Work pt. 3

Reviewed wing plans/instructions, GAP 26 pitot/AOA and GSA 28 roll servo installation instructions. Cleceoed left bottom skin onto left wing and pitot mast. Assembled roll servo components and installed in right wing; torqued and sealed all screws, bolts and nuts.