02/28/20: 2.5Hrs
1 & 2: Three pieces of SCAT tube were cut, one 17" and two 13" and all of them were prepared to install by cutting the wire inside it and bending it.
3: All of the three pieces FF-00091A, B & C were installed onto the heat muff.
4: FF-00091 B & C were connected to the vent inlets.

03/25/20 .9 Hrs
5: the three EA LV-1 heat shields were rotated directly at the radiator tube
6: the gaps in the Vent inlet assemblies were sealed with RTV. The FF-00091A was connected to the Vent-00003.
' style=