Date:  8-20-2019
Number of Hours:  11.91
Manual Reference:  
Brief Description:  17-04

08/12/19: 0.5Hrs
The area on which the wing walk doubler will be installed, was primed.

08/13/19: 2.33Hrs
The mid wing skin was prepared and the edge was bent.

08/14/19: 5.5Hrs
1. The mid wing skin was clecoed and riveted to the structure.
2. The wing walk doubler was dimpled as instructed, clecoed, and the riveting process started.

08/15/19: 0.66Hrs
3. The wing walk doubler was completely riveted.

08/16/19: 0.92Hrs
4.The the screw and rivet holes around the access hatch were dimpled #6 and #40 respectively and 10 nutplates were riveted onto them. The cover was dimpled #6 and installed.

08/20/19: 2Hrs
5. The remaining holes on the wing were riveted.