06/18/19: 2.58Hrs Worked on step 1 by trimming the aluminum tube, drilling and riveting the AN490s.
06/19/19: 1.66Hrs step 1 completed.The bearing installation was completed and the flaperon rods were given the dimensions and orientation specified.
02/18/20 .80Hrs 2. the two flapperon pushrod assemblies were passed through their corresponding oblong holes in the center section bulkheads. 3. The forward end of each flaperon pushrod assembly were attached to the F-01263A-1.