The landing gear is on. Nose gear went on first and then the mains were installed. No issues to speak of, however, the nose gear lower bearing was a challenge to put in place. Patricia helped me move the thing around. I dismantled the shipping crate to make room for the fuselage, so now the 12 foot assembly table is ready for wings, slats, and flaps.
Next on the agenda are the control systems...up to but not including the cabling as the tail feathers won't be installed until later.