Conrads X-10 Build Log
< Previous Log Entry          Next Log Entry >
' style=
Date:  10-15-2008
Number of Hours:  5.00
Manual Reference:  none
Brief Description:  Painting the Tail Cone

OCTOBER 2008
10/1/2008 ... 10/31/2008 .... Yes, I painted the Tail Cone using the Sherwin Williams DTS primer /finisher while waiting for the Wing sub-kit to arrive. This added at least 40 hours to the tail cone completion time as I had to set up a paint booth, apply multiple coats of paint and sand between coats. So total time for the Tail Code Assembly at this stage should be about 370 hours.