Date:  8-1-2009
Number of Hours:  1.00
Manual Reference:  
Brief Description:  Fuselage complete

Fuselage was moved to KGPM hanger. Fuselage now considered finished and remaining work will be considered final assembly. Total construction time now at 256 hours.