Date:  6-21-2010
Number of Hours:  1.60
Manual Reference:  
Brief Description:  HS Riveting #4

Continued riveting the HS Skin to the skeleton IAW the Van's Construction Manual, it's looking good! One more session and it should be done, I think I underestimated the time it is taking to do the riveting in last nights assumption that it would be done today!