Date:  4-25-2012
Number of Hours:  2.00
Manual Reference:  A
Brief Description:  H-Stab issues

Spent some time sorting out some issues with Tony Watkins about the placement of the stringer that goes from bulkhead 6 to 7. The manual shows it to be at 268mm to the center(A-F-020), if you put it there like I did, it will interfear with the placement of D-89. The measurement should be 268mm to the bottom of the stringer or locate D-89 first. The manual does not state this in the fuselage section where it should. Took the V-Stab off to install D-89, it's easier that way.
' style=

Stringer located exactly where manual says to put it.

Stringer located exactly where manual says to put it.

' style=

Stringer in the way

Stringer in the way

' style=

Stringer removed for D-89

Stringer removed for D-89