Date:  4-10-2015
Number of Hours:  4.00
Manual Reference:  
Brief Description:  Firewall Pass Through Complete

Finished the firewall forward wiring today. I installed the #18 single conductor shielded wire to the right mag and ran the wire through the firewall pass through. It will be connected to P1 CPC. I once more looked over the wiring and added securing ties (string loops) where needed. Once done, I completed the firewall pass through with the glass cloth/fire retardant material and two ban clamps. Tomorrow, I plan to add three of the four blast tubes. I plan to hold off on the main alternator blast tube until I figure out where the Reiff Pre-Heat system will install.
' style=

SafeAir Firewall Pass Through

SafeAir Firewall Pass Through

' style=

Left mag wired

Left mag wired

' style=

Harness secured with string

Harness secured with string