Date:  4-14-2009
Number of Hours:  5.30
Manual Reference:  W05
Brief Description:  Flaps: Both flaps COMPLETE - page W05 complete

* Riveted RH Flap. W05-01R is COMPLETE. (1.5 hrs of today's work)

* LH Flap - attached hinge (drilled, deburred, clecoed), checked everything over and riveted. Replaced 4 slightly tilted rivets. W05-01L is COMPLETE. (3.8 hrs of today's work)
' style=

Drilling LH flap hinge

Drilling LH flap hinge

' style=

Deburring inside of flap

Deburring inside of flap

' style=

Completed RH Flap

Completed RH Flap