Date:  10-24-2014
Number of Hours:  0.00
Manual Reference:  
Brief Description:  Progress so far

The kit arrived on the 1st of February 2014 and so I thought I would list the state of the build prior to commencing building the wings.
Horizontal Stabiliser complete
Elevator to commence when the replacement kit arrives (the original had a mix of Sling 2 & Sling 4 parts so the Airplane Factory is sending a new kit at no cost to me)
Vertical Stabiliser complete
Rudder complete
Right Aileron complete
Left Aileron complete but I'm not all that happy with it purely from an aesthetics point of view
Right Flap complete
Left Flap yet to be completed due dent to the skin to be assessed by panel expert
Fuel tanks are complete as they were purchased as a factory quick build option
' style=

Components in house roof storage

Components in house roof storage