Date:  3-25-2021
Number of Hours:  10.00
Manual Reference:  
Brief Description:  Main Gear Installation

Over the last few weeks I've done quite a bit of preparation for painting the fuselage & main landing gear leg & had two fairly major changes of mind. Firstly PGC & I have decided to purchase the latest version of the engine cowls as the coolant & oil cooling is much improved with them so the work I have done on my cowl has been for nought and secondly, I've decided to complete the installation of the main gear prior to painting. Last Monday GAM & PGC helped me remove the engine & place it back in its crate, thank you both very much, we then swapped the main undercarriage leg & installed the serviceable unit, I now need to modify the doorway to my workshop as the gear is too wide to pass through the existing door.

A milestone reached today by installing the last skin.
' style=

Preparing to rivet

Preparing to rivet

' style=

Done, last skin installed

Done, last skin installed

' style=

Almost ready to go to the paint shop

Almost ready to go to the paint shop

' style=










Copyright © 2001-2024 Matronics. All Rights Reserved.