Date:  1-8-2021
Number of Hours:  9.00
Manual Reference:  
Brief Description:  Deice testing and rewire

During system testing tried the company supplied testing connectors. They were heavier gauge power wire. Using the testing wire the time between the double "Knock" on the left wing went from much slower than the L wing (3.5 sec vs 1 sec) to both about a 1 sec delay between the "knocks".Thereforer I decided to rewire the Can bus and power connection between the Controllers so as to add 18 gauge power wire which replaced the 22 gauge power wire in the suppliied connector cables. Pulled new wire and made about half the connections.