Rans S-7S Courier
S7S
Wing LH
9-19-2009
< Previous Log Entry
Next Log Entry >
Date:
9-19-2009
Number of Hours:
1.00
Manual Reference:
05C-01
Brief Description:
Aileron Bellcrank Installation
Transfer drilled the compression tube and the compression tube doubler at the predrilled locations with a #11 drill, used the bearing mount blocks as a guide.
Bolted the entire assembly to the wing frame as per parts manual.
LH Aileron Bellcrank
< Previous Log Entry
Next Log Entry >
SITE NAVIGATION
Contact Builder
S7S Home
Category
# Logs
# Hours
All
197
810
Control Systems
7
18
Covering
46
251
Delivery
4
21
Fuselage
21
45
Gear
3
4
LH Wing
11
42
Painting
50
235
Wing LH
11
42
Wing RH
22
76
Wings
22
76