KitLog pro

Powered By Kitlog Pro v2.0

Dave's RV-10 Build Log
' style=
Date:  9-6-2019
Number of Hours:  6.50
Manual Reference:  
Brief Description:  Installed GTP 59 ; Installed Throttle Quadrant

Installed the GTP 59 outside air temperature probe into the left wing and ran the wires to the wing root. Crimped pins to the wires at the wing root and installed them in a DB-9 connector. Crimped pins to the wires coming from the fuselage to the GTP 59 OAT probe at the base of the left wing area and installed them in a mating DB-9 connector.

Installed the throttle quadrant to the tunnel cover. Realized that the mixture & prop cables had gotten crossed so had to remove the left lower panel piece and the center breaker panel in order to cross them back to the correct alignment with the quadrant. Installed the cables to the quadrant and adjusted them to give full control travel with a bit of cushion in the quadrant throws.
' style=