Date:  9-21-2016
Number of Hours:  8.00
Manual Reference:  
Brief Description:  Fiberglass Top; Baggage Door

Completed baggage door installation. Reached the 2 rivets at the top of the hinge frame by using the offset rivet tool as a bucking bar to drive the AN470AD4 rivets.
Installed weather stripping onto the door flange. Had to cut the top strip down in order to have the door fit flush.
Installed the Left baggage cover forward of the door. The QB had the nut plates already installed, which required drilling them out in order to install them with the baggage cover as called for in the drawings.

Cut and "sanded" the right door opening of the fiberglass cabin top.

Started to install the fuel pump and filter (received on Monday). Had to remove the fuel selector valve in order to replace the T installed per the plans to allow for a return line with a 45 deg. ell since the new pump doesn't require a return line. With the control sticks and associated hardware now in place, removing the valve was difficult.
' style=

Baggage Door Installed

Baggage Door Installed

' style=

Door Interior

Door Interior

' style=

Trimmed Door Opening

Trimmed Door Opening

' style=










Copyright © 2001-2024 Matronics. All Rights Reserved.