Dave's RV-10 Build Log
' style=
Date:  8-25-2016
Number of Hours:  8.50
Manual Reference:  Pg 33-6, 7, & 8
Brief Description:  Baggage Area

Riveted the baggage area floors per drawings. Had to remove the floors after clecoing then down in order to dimple a few holes that had been missed by the Vans QB team. (Most of the holes requiring dimples had been dimpled, as had the ribs under the floors, however there was one area which should have been dimpled which hadn't been done. Luckily I noticed before starting to rivet the floors down.)

Riveted the baggage floor angles to the floor and the side skins.

Installed and riveted the baggage door seal channels and close out panel.

Clecoed the right baggage cover and back panel, and drilled holes for both as called for in the plans. Did not rivet the bottom of the F-1028 baggage bulkhead channel, but clecoed instead as I don't want to have this channel in the way when I install the Garmin auto pilot servo mounts (ordered from Aircraft Spruce), which I should be able to do next week as they have shipped.
' style=










Copyright © 2001-2024 Matronics. All Rights Reserved.